Cap. 357D 《1990年供電網絡(法定地役權)(更正獲准計劃)令》Electricity Networks (Statutory Easements) (Rectification of Approved Scheme) Order 1990

生效中
版本日期: 2019-12-12

Electricity Networks (Statutory Easements) (Rectification of Approved Scheme) Order 1990

(Cap. 357, section 7)

(Enacting provision omitted—E.R. 6 of 2019)

[2 March 1990]

(Format changes—E.R. 6 of 2019)

1. Citation

This order may be cited as the Electricity Networks (Statutory Easements) (Rectification of Approved Scheme) Order 1990.

2. Interpretation

In this order—

approved scheme (獲准計劃) means the scheme specified in the Schedule; power company (電力公司) means the China Light & Power Company, Limited.

3. Rectification of approved scheme

Subject to section 7(3) of the Ordinance, the approved scheme shall have effect as rectified by the agreement made between the power company and the Secretary for Planning, Environment and Lands and deposited in the Land Office on 17 January 1990.

Schedule — Approved Scheme

[para. 2]

400 kV Transmission Lines, Tai Po to PRC Border and Yuen Long to PRC Border; 15 December 1988. Approved by the Secretary for Lands and Works and deposited in the Land Office on 4 January 1989.