HCAL184/2002 SHIU WING STEEL LTD v. DIRECTOR OF ENVIRONMENTAL PROTECTION - LawHero
HCAL184/2002
高等法院(行政)Burrell J29/9/2003
HCAL184/2002
由此
A A
HCAL184/2002
B B
IN THE HIGH COURT OF THE
C HONG KONG SPECIAL ADMINISTRATIVE REGION C
COURT OF FIRST INSTANCE
D D
CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST
E NO.184 OF 2002 E
F --------------------- F
BETWEEN
G G
SHIU WING STEEL LIMITED Applicant
H H
I and I
J J
DIRECTOR OF ENVIRONMENTAL PROTECTION Respondent
K
AIRPORT AUTHORITY OF HONG KONG Interested Party K
L ---------------------- L
M Before : Hon Burrell J in Court M
Dates of Hearing : 5, 8-11, 15-17 September 2003
N N
Date of Judgment : 30 September 2003
O O
-------------------------
P JUDGMENT P
-------------------------
Q Q
1. The Hong Kong Airport Authority (“HKAA”) needs a new
R R
permanent air fuel farm (“PAFF”). During the late 1990’s many possible
S sites were considered. The result was that a site known as Tuen Mun 38 S
was chosen as the most suitable. Accordingly, they commenced the
T T
numerous procedures necessary to embark on such a project. If all the
U U
V V
由此
- 2 -
A A
procedures are successfully completed they have estimated that the PAFF
B B
would be operational by 2006.
C C
2. One of the many procedures is compliance with Cap.499, the
D D
Environmental Impact Assessment Ordinance (“EIAO”). The EIAO sets
E out a number of steps to be followed by the proposed developer. As part E
of their purported compliance with the EIAO the Director of
F F
Environmental Protection (“the Director”) has made decisions which have
G permitted the continuation of the project. Two of his decisions are now G
the subject of judicial review by the applicant (“SWS”) in these
H H
proceedings. The first decision was made on 2 August 2002. That was
I a decision to approve an EIA report submitted by the HKAA in relation to I
J
the PAFF for the Airport under section 8(3) of the EIAO. The second J
was on 28 August 2002. This was the decision under section 10(2) to
K K
grant an Environmental Permit with conditions (pursuant to section 10(5))
L
to the HKAA. L
M M
STATUTORY FRAMEWORK
N N
3. The EIAO is a relatively new, relatively short but very
O
important ordinance. It is clear from an overview of the whole enactment O
that it has a dual objective. The “overview” reveals a number of steps
P P
that a developer must take, each of them has a specified time limit. The
Q result is a fairly tight timetable to which both the developer and the Q
director must conform. The dual objectives strike a balance. The
R R
EIAO’s primary concern is the protection of the environment. Its
S framework provides a regime in which, and this is the second objective, S
important projects may be completed in a timely and efficient way,
T T
provided all the requirements of the EIAO are complied with. The
U U
V V
由此
- 3 -
A A
Tribunal’s report in the recent “Long Valley” appeal (KCR Corp. v.
B B
Director of Environmental Protection; EIA Appeal Board 2 of 2000)
C helpfully commented as follows : C
D “… The Ordinance gives the EIA process a legal structure. It is D
not a process which lies comfortably within a detailed legal
framework. Much of its success depends therefore upon the
E E
manner in which it is implemented within the outline structure
provided assisted by the Technical Memorandum. The
F consequence is that all involved are learning how best the F
various steps required can be implemented. … There are two
main matters of public interest involved. Both are important.
G The first is the public interest in the protection of the G
environment upon which the quality of life in Hong Kong will
H increasingly depend. The second is the public interest in H
ensuring that major designated projects are brought to fruition in
a timely and efficient manner. The time constraints put upon
I the Director for steps in the process and for his decisions show I
that the Ordinance aims to satisfy both interests.”
J J
K
4. The key provisions in the ordinance which demonstrate this K
step by step approach and dual objectives are these :
L L
(1) By section 4 certain projects (such as the PAFF) become
M “designated projects”. M
N (2) By section 5 the developer applies to the Director for a study N
brief (“SB”) and at the same time submits and advertises a
O project profile. The Director also informs the Advisory O
Council on the Environment (“ACE”). ACE is an
P P
independent advisory committee comprising 23 members. It
Q is a sort of watch-dog and is peculiar to Hong Kong in Q
environment impact regimes. ACE and the public have
R R
14 days within which it may comment on the project profile.
The Director must issue the SB within 45 days.
S S
(3) By section 6 HKAA prepares an EIA report in accordance
T T
with the SB (section 6(1)) and delivers it to the Director.
U U
V V
由此
- 4 -
A A
Within 60 days thereafter the Director decides if the report
B B
meets the requirements of the SB and the technical
C memorandum (“TM”) (section 6(3)). If he does, the report is C
then made available for a 30-day public inspection.
D D
(4) By section 7(5) ACE may give its comments within 60 days.
E E
(5) By section 8(3), within 30 days after the public inspection the
F
Director either approves, or approves conditionally or rejects F
the EIA report.
G G
(6) By section 10 HKAA may apply for the environmental permit
H for the project which the Director may grant (under H
section 10(2)).
I I
(7) By section 16 the Secretary for the Environment Transport
J and Works may issue TM setting out principles, procedures, J
guidelines, requirements and criteria for whether the EIA
K report meets the requirements of the SB. K
L L
5. In the present case SWS’s key complaint is that the Director’s
M M
decision to approve the report (section 8(3)) and grant the permit (section
N 10(2)) were either unlawful and/or Wednesbury unreasonable because the N
report did not meet the requirements of the SB and TM. SWS in this
O O
framework has no right of appeal against the Director’s decision. Only a
P party to the project itself has such a right. The SB and the TM are key P
documents. The TM is the framework of criteria out of which an SB is
Q Q
created. The SB is the template of objectives and obligations against
R which the EIA report is prepared. They will both be considered in more R
detail later in this judgment.
S S
T T
U U
V V
由此
- 5 -
A A
BACKGROUND
B B
6. The background to the issues in this judicial review is best
C C
understood by reference to a chronology of key events.
D D
7. In April 2001 HKAA applied with a project profile for an SB.
E E
On 31 May 2001 the Director issued the SB and HKAA engaged Mouchel
F to prepare the EIA report (in June 2001). The report took nearly a year to F
produce. It is 480 pages long. The “Hazard to Life” section, with which
G G
this judicial review is concerned, runs to 55 pages.
H H
8. The report was submitted to the Director for his consideration
I I
under section 6 on 3 May 2002. It had been signed as a complete report
J on 26 April 2002. The day before, 25 April, an important meeting had J
taken place between representatives of the Director and HKAA. At this
K K
meeting a decision was made that one of the particular hazards to life that
L the report had identified, namely an instantaneous loss of 100% of the L
contents of a fuel tank, need not be quantitatively assessed. It was
M M
decided that it was sufficient to assess such a scenario qualitatively. This
N N
decision lies at the heart of this judicial review.
O O
9. In short, a quantitative assessment requires a statistical
P P
analysis. It results in a numerical representation of the likelihood of
Q deaths occurring from a particular type of accident occurring and at what Q
frequency and in what numbers. A qualitative analysis, on the other hand,
R R
is more subjective. It does not require an input of statistical data. It is
S an assessment made by experts in the field. It is the report’s failure to S
carry out a quantitative assessment (“QRA”) of the 100% instant loss
T T
scenario upon which SWS relies as the lynchpin to their case. They
U U
V V
由此
- 6 -
A A
submit that failure rendered the report deficient so that the Director’s
B B
approval of it was unlawful.
C C
10. During May, June and July the various provisions of the
D D
EIAO were complied with. The report entered the public domain. SWS
E wrote its letter of complaint on 13 July 2002. The key extracts from that E
letter, which summarize SWS’s opposition to the project which pre-date
F F
the Director’s decision are as follows :
G G
“‘… SWS believes that the EIA report on the proposed PAFF has
not addressed adequately the impact of the PAFF on the Mill as
H H
an existing user of a high temperature operation.’
I ‘Spillage I
The effects of a major spillage incident on water at both the
J Castle Peak Power Station in the proximity and the Mill would J
be catastrophic. Both facilities use seawater intakes for
cool-down process, but no reference is made in the EIA report as
K K
to how the location of the jetty, the discharge of the fuel and
anchoring of tankers will affect these. Besides, the impact of an
L oil spill on adjacent industries have not been considered in L
respect of the seawater intake.’
M ‘Risk of Fire M
In the EIA report, several references are made to the potential
N N
emissions from both the transfer (working losses) and storage
(standing storage losses) of the aviation fuel. Yet the total
O volume of the likely emissions is not discussed. The more O
important shortcoming is that the EIA Report has not made
references to the fact that the Mill is sited immediately adjacent
P to the proposed PAFF and will engage in processes which P
o
involve very high temperatures (up to 1300 C). The siting of a
Q facility which discharges aviation fuel vapours immediately Q
adjacent to a facility of very high temperature processes and
furnace operations is unsafe. In this case, any spillage incident
R would be catastrophic.’” R
S S
T T
U U
V V
由此
- 7 -
A A
11. ACE met to consider the report and all public comments on
B B
29 July 2002. It declared that it was satisfied that the risk was within
C acceptable levels and endorsed the report. C
D D
12. On 2 August 2002 the Director approved the report under
E section 8(3). The section 10(2) permit was granted on 28 August, with E
conditions.
F F
G 13. At some stage during this process SWS had commissioned its G
own report. That report (the “Maclnnis” report) is dated 16 October 2002.
H H
It was sent to the Director on 21 October. The accompanying letter
I summarizes the report’s conclusions as follows : I
J “(1) The EIA Report does not meet the requirements of the J
Technical Memorandum.
K K
(2) All reasonable hazardous scenarios have not been
considered, and certain assumptions/methodologies used in
L the EIA are questionable and/or inaccurate. L
(3) Construction of the Proposed PAFF at Area 38 may produce
M hazardous conditions that would result in a greater hazard M
to life than intended by the EIA Ordinance.
N N
The points raised have been put to the Town Planning Board and
the Airport Authority. Given the nature of the risks Shiu Wing
O have decided that it would be in the interest of all concerned to O
make the report available in its entirety. The Airport Authority
have been asked to confirm that it has thought of these risks and
P P
that it has adequate measures in place to safeguard safety.
Q Safety Q
As stated above, this is obviously a very special situation, and
R strict compliance with all required procedure and technical R
memoranda is vital. Shiu Wing have no wish to be obstructive,
but we clearly have a major interest in the outcome of your
S decision. The Macinnis Report confirms that the proximity of S
the Steel Mill’s operations is not discussed in the EIA report but
T may be of importance if there was a fuel spill inside or outside T
the bund area, and that there are a number of possible ignition
U U
V V
由此
- 8 -
A A
sources which have not been considered. In all the
B circumstances, you should not hesitate to suspend, vary or cancel B
the permit if you are in any doubt regarding the information
previously provided, or the safety of the project.
C C
Notwithstanding the importance of the project, we would suggest
that you cannot be too cautious in these circumstances.”
D D
E 14. After a brief exchange of correspondence between the various E
parties SWS issued its notice of application for judicial review on
F F
1 November 2002. Leave was granted by Hartmann J on 13 November.
G G
15. Since the granting of leave further reports from all sides have
H H
been prepared. In response to Maclnnis the HKAA filed a report by AEA
I Technology (“AEAT report”) on 5 February 2003, and the Director filed a I
report from Shell Global Solutions (“Shell”) on 12 February. AEAT
J J
concluded that :
K K
“(a) None of the issues raised by Macinnis identify errors or
omissions in the EIA Report which AEAT consider would
L significantly affect the predicted risk levels, which lie L
within the acceptable region of the criteria established in
M Annex 4 of the Technical Memorandum; … M
(d) AEAT consider that the EIA Report identifies and discusses
N all reasonable hazardous scenarios associated with the N
PAFF. In particular, AEAT do not consider it was
necessary for the EIA Report to consider specifically the
O O
scenarios suggested by Macinnis in which : (a) hot
surfaces within the Steel Mill could ignite a release from
P the PAFF; (b) smoke carrying inflammable vapours could P
ignite on reaching the Steel Mill; and (c) hot gases emitted
from the Steel Mill could lead to ignition of Jet A-1 at the
Q PAFF. AEAT consider that these potential scenarios are Q
reasonably covered within the general scenarios adopted
R by the EIA Report; and R
(e) AEAT consider that the assumptions and methodologies
S used in the EIA Report are reasonable within the scope of S
the assessment. In particular, AEAT consider that the
thermal impact criterion used in the EIA Report is a
T T
reasonable approximation for the PAFF, which will not
U U
V V
由此
- 9 -
A A
significantly affect the predicted risk levels compared
B with the criteria established in Annex 4 of the Technical B
Memorandum, when compared to other reasonable
calculation methods.’
C C
Based on this review, AEAT consider that none of the issues
D identified by Macinnis would change the key conclusion in D
paragraph 10.9.7 of the EIA Report, namely that ‘Based on the
analysis presented in this section, including the
E recommendations, it can be concluded that the offsite individual E
and societal risks posed by the activities at the PAFF tank farm
and associated marine environment are acceptable according to
F F
the criteria set out in Annex 4 of the EIAO-TM (ie the Technical
Memorandum).”
G G
H 16. Shell concluded that : H
I “The EIA for the PAFF at Tuen Mun Area 38 has been I
challenged for not taking sufficient account of the neighbouring
Shiu Wing Steel Mill. Although the presence of the mill and its
J workforce is specifically mentioned, Macinnis claim that the J
effect modelling described in the EIA is not sufficiently
K conservative, and that worse case scenarios deemed incredible by K
the authors of the EIA should have been included.
L It has been shown in this report that the extra scenarios L
mentioned by Macinnis are indeed incredible, and that the
scenarios and assumptions in the EIA Report are comprehensive
M M
and robust. The worst-case scenario addressed in the EIA (tank
overfill) is the worst foreseeable, and was modelled
N conservatively in that the assumed damage was significantly N
worse than is observed in practice. The hazard to life
assessment in the EIA remains sufficient, and retains its validity.
O O
Even if the extra hypothetical scenarios postulated by Macinnis
P
after the EIA was published were to be included as a sensitivity
P
study, they do not pose a risk to the people in the steel mill or to
its structure, and the total risk for the PAFF is still acceptable.”
Q Q
R 17. SWS were clearly not satisfied with these conclusions. As a R
result, their notice of application was re-amended and a further report
S S
filed — the “HSL” report (Health & Safety Laboratory, a much respected
T T
U U
V V
由此
- 10 -
A A
UK organization) written by Mr Marc McBride. A summary of that
B B
report’s findings are :
C C
(1) The Hazard Assessment is fundamentally flawed because it
D fails to identify and assess the risk associated with a D
catastrophic failure of one of the aviation fuel storage tanks,
E E
i.e. instantaneous loss of 100% of the tank contents. This is
contrary to common practice for Hazard Assessment studies
F F
in Hong Kong and published international good practice.
G Furthermore, there have been past occurrences of catastrophic G
tank failure relevant to the PAFF.
H H
(2) The Hazard Assessment fails to comply with the requirements
I of the EIA Study Brief because it does not identify all I
hazardous scenarios, in particular the catastrophic tank failure
J J
scenario.
K (3) HSL’s assessment is that this scenario could cause almost K
200 fatalities at the SWS site, due to the significant fraction of
L L
aviation fuel which would overtop the bund (as demonstrated
M by theoretical models, large scale experimental studies and M
past incidents), together with the strong likelihood of ignition
N N
associated with activities at the steel plant.
O (4) The Hazard Assessment grossly underestimates the risk O
associated with the proposed PAFF. Using the figure
P P
contained in section 10.5.2 of the Hazard Assessment on the
frequency of catastrophic tank failure, the overall risk for the
Q Q
PAFF (2040 case) is calculated to lie with the upper ‘ALARP’
R region of the Risk Guidelines, rather than in the “acceptable” R
region as the EIA report would suppose (ALARP stands for
S S
As Low As Reasonably Practicable).
T T
U U
V V
由此
- 11 -
A A
(5) There is a significant off-site risk associated with the
B B
proposed PAFF. Compliance only with minimum separation
C distances does not provide an acceptable basis for the siting of C
the PAFF. Good practice would require that the decision as
D D
to its siting be risk-based, having regard to the location and
E surroundings of the installation, irrespective of separation E
distances.
F F
(6) The proposed PAFF design does not comply with relevant
G international standards, namely the Institute of Petroleum G
Model Code of Safe Practice, Part 2 : Design, Construction
H H
and Operation of Distribution Facilities.
I I
SWS acknowledge that (1) and (2) are inaccurate. The EIA report did
J identify the 100% instantaneous loss scenario and it did assess it. What it J
did not do is assess it quantitatively. The report had concluded that the
K K
worst case scenario was a 10% loss when it said “The catastrophic failure
L of the tank is therefore assumed to result in a release of 10% of tank L
contents (i.e. about 3,900 m3) on to the bund”.
M M
N 18. There is no complaint that the assessment of the “10% worst N
case scenario” was not fully addressed in considerable detail in the report.
O O
The conclusion that the QRA be confined to the 10% scenario is preceded
P by a wealth of scientific data. P
Q Q
19. I have set out the conclusions to these reports for two reasons.
R Firstly, to demonstrate one of the few things about which there is R
agreement between the parties in this case, namely that there is a
S S
difference of opinion between the experts. (In passing, it is also agreed
T that the scientific or technical debate between the experts cannot be and is T
U U
V V
由此
- 12 -
A A
not to be resolved by the court. The parties are unanimous that the court
B B
should not get involved with the debate between the experts). Secondly,
C the filing of these reports (together with two affirmations on behalf of C
SWS from Mr T. Maylor and Libor Rostik which provide, inter alia,
D D
evidence about the workings of the steel mill) prompted a preliminary
E hearing which was heard in this court on 24 July 2003 in which SWS E
applied for leave to re-amend the notice of application and file the HSL
F F
report and the two affirmations. The application was opposed. At the
G end of a relatively short hearing, which only scratched the surface of the G
issues and the reports, I granted leave to re-amend and admitted the fresh
H H
evidence relied on by SWS de bene esse. One reason for admitting it
I de bene esse was to give the court an opportunity at the full hearing to I
J
consider the report and its relevance in greater depth. This has now J
happened and I consider the matter more fully later in this judgment.
K K
L
20. Throughout the above events, many affirmations and L
affidavits have been filed. 12 deponents have filed 18 affirmations
M M
totalling 177 pages.
N N
THE ISSUES
O O
21. SWS on the one hand and the Director and HKAA on the
P P
other do not agree what the issues to be resolved by the court are. The
Q prime reasons for the disagreement are that : Q
R
(a) there is no consensus as to the legal boundaries set by judicial R
review proceedings. SWS submit they are changing and
S widening, S
T T
U U
V V
由此
- 13 -
A A
(b) the admissibility of the HSL report remains an issue.
B B
Without it the issues are narrower.
C C
D 22. Defining the issues is a highly significant exercise. In some D
ways it goes a long way towards determining the outcome of the judicial
E E
review itself.
F F
23. Erring on the safe side all counsel have addressed the court on
G G
all issues, that is, those advanced by SWS. Counsel’s submissions have
H been comprehensive. Mr Charles Haddon-Cave, QC and H
Mr Nigel Pleming, QC leading Mr Anthony Chan, SC have appeared for
I I
SWS. The Director has been represented by Mr Benjamin Yu, SC
J leading Mr Anthony Ismail and Ms Gladys Li, SC has represented HKAA. J
Their instructive and helpful skeleton submissions run to 250 pages. The
K K
research of all three legal teams has been impressive. Whether the court
L proceeds therefore on the wide list of issues contended for by SWS or the L
more conservative list proposed by the Director is a very important
M M
decision. Mr Haddon-Cave’s list of issues and consequential issues pose
N 24 questions to be answered. Mr Yu lists five issues. N
O O
24. As will be seen from what follows in this judgment, and after
P anxious deliberation, I have preferred the narrower approach submitted by P
the respondent and HKAA. I will not, therefore, set out all the issues as
Q Q
advanced by SWS. Mr Pleming, an acknowledged and respected expert
R in administrative law commenced his submissions as follows : R
S “ This is, I hope your Lordship will accept, a very important S
case for environmental law in Hong Kong. Your Lordship’s
T
judgment will no doubt significantly assist in a number of ways, T
apart from assisting the particular parties.
U U
V V
由此
- 14 -
A A
Could I respectfully suggest what those ways might be.
B First of all, it will be the first opportunity for the court in Hong B
Kong to express its view as to the meaning, if it has a view, and
can express one, on the language and the purpose -- and
C C
I emphasise the purpose -- of the ordinance and the technical
memorandum.
D D
The second area of significance is that your Lordship’s
judgment will provide an opportunity for the determination of
E the true role and expectations of the public. By ‘the public’ E
I also include the advisory council as the representative of the
public, in what Mr Haddon-Cave has described so far as, and
F F
I here add as part of my submissions, a tripartite process.
G The third area of importance is that your Lordship’s G
judgment may be a step in the direction of determining the
standards to be applied in the approval process. I cover by that
H all stages in the ordinance, from compliance through approval to H
permit, the degree of rigidity or laxity that is involved.”
I I
J 25. The view of this court is that first instance judgments should J
be primarily, if not solely, directed towards the decision which the parties
K K
want to know. Should that decision necessitate matters of statutory
L construction or applications of principle then so be it. However, such L
determinations should be confined to only those which are necessary for
M M
the court to carry out its primary task which in this case is to apply the
N Hong Kong law of judicial review to the two decisions under challenge N
and decide if any grounds have been made out to review them.
O O
P 26. It seems to me therefore that the respondent’s issues better P
reflect the task of this court in this case. They are :
Q Q
(1) Whether the evidence in the form of expert reports are
R R
admissible in judicial review proceedings by way of exception
S under R. v. Secretary of State for the Environment ex parte S
Powis [1981] 1 WLR 584?
T T
U U
V V
由此
- 15 -
A A
(2) Whether the Director acted lawfully in approving the EIA
B B
report and allowing the project proponent not to carry out a
C quantitative risk assessment on instantaneous release of 100% C
of a tank content?
D D
(3) Whether the Director acted reasonably in the public law sense
E in approving the EIA report and allowing the project E
proponent not to carry out a quantitative risk assessment on
F F
instantaneous release of 100% of a tank content?
G (4) Whether the challenge that the EIA report does not comply G
with the SB and the TM is out of time?
H H
(5) Whether the court in the exercise of discretion should grant
I relief having regard to : I
J (a) delay; J
(b) prejudice to the Airport Authority;
K K
(c) prejudice to good administration.
L L
M 27. It will be noted that the first issue concerns the admissibility M
of the HSL report. I therefore deal with this as a preliminary issue next.
N N
Before doing so I should add that SWS’s list of issues has not been
O shredded. On the contrary, they remain a useful guide to structure this O
judgment. The 24 questions have been helpfully grouped under the
P P
six heads of challenge contained in the re-amended notice of application.
Q I propose to deal with each of those challenges separately, although in Q
many instances, briefly. Before, therefore, I turn to the important
R R
question of the admissibility of the HSL report, it is convenient to set out,
S in summary form, SWS’s six heads of challenge. S
T T
U U
V V
由此
- 16 -
A A
SWS’S GROUNDS OF CHALLENGE
B B
28. SWS’s case is that the EIA report is deficient in that it failed
C C
to comply with the legal requirement of EIAO, in particular the
D requirements of the SB or TM. If that proposition is correct the D
Director’s approval of it, under section 8(3) was unlawful because it was
E E
not a proper or valid report under section 6. For the same reason the
F section 10(2) permit was not lawfully granted either. F
G G
29. Six separate grounds are identified. In truth, grounds 2 to 6
H flow from ground 1. Ground 1 is the crux of the matter. Ground 1 H
depends on how the ordinance is construed. Counsel for SWS
I I
acknowledge that there is considerable overlap between the various
J grounds. In spite of submissions to the contrary I am not persuaded that J
any of grounds 2 to 6 can be freestanding.
K K
(a) Ground 1 is described as the Quantitative Risk Assessment
L L
argument (“the QRA argument”). Paragraph 3.3.10 of the
M SB states : M
“3.3.10 Hazard To Life
N N
3.3.10.1 The risk to the life, including the workers of nearby
plants, due to marine transport, jetty transfer, tank farm
O storage and pipeline transfer of aviation fuel shall be O
assessed. The Applicant shall follow the criteria for
P
evaluating hazard to life as stated in Annexes 4 and 22 P
of the TM in conducting hazard assessment and
include the following in the assessment:
Q Q
(i) identification of all hazardous scenarios associated
with the marine transport, jetty transfer, tank farm
R storage and pipeline transfer of aviation fuel, which R
may cause fatalities;
S (ii) execution of a Quantitative Risk Assessment S
expressing population risks in both individual and
societal term;
T T
U U
V V
由此
- 17 -
A A
(iii) comparison of individual and societal risks with the
B Criteria for Evaluating Hazard to Life stipulated in B
Annex 4 of the TM; and
C (iv) identification and assessment of practicable and cost C
effective risk mitigation measures as appropriate.”
D D
In short, having identified a 100% instantaneous loss as a
E E
scenario under (i), they were required to execute a QRA in
F respect of it. Once identified the TM required that a QRA F
must be done in respect of all identified hazards.
G G
(b) Ground 2 is described as the Material Facts argument. It is
H submitted that prior to making his decision the Director failed H
to acquaint himself with the nature of the works at the steel
I mill and the number of people who worked there. I
J (c) Ground 3 is the Applicant’s letter argument. It is submitted J
that the Director disregarded SWS’s letter of complaint dated
K K
13 July 2002.
L (d) Ground 4 is the 25 April 2002 meeting argument. The L
decision not to carry out a QRA in respect of 100%
M M
instantaneous loss was taken at a meeting between the
Director and HKAA just prior to releasing the report. It is
N N
submitted that the effect of this decision was to remove a key
O issue, namely 100% catastrophic failure, from public debate O
and consideration.
P P
(e) Ground 5 is the Safeguards argument. It is submitted that
Q the Director should not have relied on the various safeguards Q
that were incorporated into the design and operation of the
R R
PAFF when deciding not to do a QRA for the 100% loss
S scenario. S
(f) Finally ground 6 is the Conditions argument. It is submitted
T T
that a condition which was imposed on the granting of the
U U
V V
由此
- 18 -
A A
permit (“Permit Condition 3.9”) was unlawful as it fell
B B
outside Schedule 4 of the EIAO.
C C
D 30. Before considering these grounds in more detail, I now turn to D
the preliminary issue of the admissibility of the HSL report.
E E
F THE HSL REPORT — ADMISSIBILITY F
G 31. The quality and expertise of the HSL report, together with G
independence and excellent reputation of HSL itself is not doubted.
H H
I 32. The report has been admitted de bene esse. The court has I
now had a full opportunity (as opposed to a superficial opportunity at the
J J
preliminary hearing on 23 July) to consider the purpose and content of the
K report in the light of issues to be determined. K
L L
33. Counsel for SWS submit that the report and the fresh
M evidence is admissible as an exception to the general rule. Authorities M
and learned texts have been cited in support of the general proposition that
N N
the circumstances in which post decision materials can be admitted is
O widening. Bearing in mind the importance and complexity of this case, it O
is submitted that the court should lean in favour of including it rather than
P P
excluding it.
Q Q
34. The general rule can be found in R. v. Secretary of State for
R R
the Environment ex parte Powis [1981] 1 WLR at p.595 :
S S
“Finally there was an application on behalf of the tenant to admit
fresh evidence which the Divisional Court had refused to admit.
T T
Like the Divisional Court we considered the evidence de bene
U U
V V
由此
- 19 -
A A
esse. What are the principles on which fresh evidence should
B be admitted on judicial review? They are (1) that the court can B
receive evidence to show what material was before the minister
or inferior tribunal : … (2) where the jurisdiction of the minister
C C
or inferior tribunal depends on a question of fact or where the
question is whether essential procedural requirements were
D observed, the court may receive and consider additional evidence D
to determine the jurisdictional fact or procedural error : … and
(3) where the proceedings are tainted by misconduct on the part
E of the minister or member of the inferior tribunal or the parties E
before it. Examples of such misconduct are bias by the
F decision making body, or fraud or perjury by a party. In each F
case fresh evidence is admissible to prove the particular
misconduct alleged : …”
G G
H
35. There are many examples of the application of the general H
rule in Hong Kong. For example in Nguyen Ho v. Director of
I I
Immigration [1991] 1 HKLR 576, Cons VP said :
J J
“From that exposition alone I am satisfied that unreasonableness
as a factor by itself, what might be termed the second limb in
K Wednesbury, can only be judged with regard to what was known K
to the inferior tribunal at the time.”
L L
36. In Yu Chee Yin v. Commissioner of ICAC [2001] 2 HKC 91 at
M M
104, Hartmann J said :
N N
“It is common cause that the evidence contained in the
affirmations was not before the Commissioner when he made his
O decision. Indeed, that is the foundation of the applicant’s O
third challenge. But a claim of unreasonableness in the
P ‘Wednesbury’ sense is judged in light of the information that was P
before the decision maker when he made the decision. It is not
judged in the light of information that has only become known
Q after the event.” Q
R R
37. SWS submits there are four reasons to treat the HSL report as
S an exception to the general rule. I consider it sufficient to simply recite S
T T
U U
V V
由此
- 20 -
A A
those four reasons without reviewing the many authorities to which I was
B B
referred in the course of submissions.
C C
38. First, where it is alleged that the decision maker failed to take
D D
account of a relevant fact, evidence can be admitted to show (a) why it is
E relevant and (b) the significance of the disregarded material in the E
decision-making process.
F F
G 39. Second, this case falls within the second head of Powis : G
Where the jurisdiction of the decision maker depends on a question of fact
H H
evidence is admissible to challenge the fact and to show that he had no
I jurisdiction or authority to do what he did. I
J J
40. Third, there is an “emerging” category for admission of
K K
material not before the decision-maker. Where a decision is made in
L
ignorance of or contrary to the true facts, evidence is admissible to L
demonstrate the true facts upon which the decision should have been based,
M M
provided that it is shown that the facts placed before or found by the
N decision maker were “plainly wrong”. N
O O
41. Fourth, where it is alleged that the defendant has failed in its
P duty to acquaint itself with relevant information, it will often be essential P
for the applicant to demonstrate (in a case such as this by reference to both
Q Q
factual and expert evidence) that there was material with which the
R decision maker should have been acquainted at the time of the relevant R
decisions but was not. Here, that category covers the true factual
S S
situation at the steel mill described by Maylor and Rostik.
T T
U U
V V
由此
- 21 -
A A
42. In short it is argued that HSL establishes that a QRA on the
B B
100% loss scenario could have been carried out, but was not, and had it
C been the Director’s decision could have been different. C
D D
43. I have considered the authorities relied on by SWS and in
E particular the passage from Fordham Administrative Law under the E
heading “Fresh evidence in Judicial Review”. For the reasons which
F F
follow I have come to the conclusion that the report is not admissible
G because the grounds for categorizing it as an admissible exception to the G
general rule have not been made out. Any apparent inconsistencies
H H
between the reasons for excluding it now and the reasons for admitting it
I de bene esse on 23 July stem, quite simply, from the full nature of the I
J
argument in this hearing compared with the brief nature of the argument in J
the former hearing. It is worth mentioning also that SWS’s primary
K K
argument, namely that the section 8(3) decision was unlawful because the
L
EIA report was deficient is a question of construction and remains in tact L
with or without HSL.
M M
N 44. I agree with the general argument advanced by the Director N
and HKAA that, in reality, the HSL report is an expert opinion in support
O O
of SWS’s latest case (I deal later with the point that SWS’s latest case is
P significantly different from its original case upon which leave for judicial P
review was granted). As such, it merely reinforces the undoubted truth
Q Q
that expert opinions differ. The fact that a QRA was not being done on
R the 100% loss scenario was known from 3 May 2002. The alleged R
deficiency, which is the crux of the HSL report, could have been placed
S S
before the Director before he made his decision but was not. SWS submit,
T as they must do, that the report contains fact not opinion which should T
U U
V V
由此
- 22 -
A A
have been before the Director. To separate fact from opinion in this
B B
particular report is almost impossible. Taken as a whole its conclusions
C plainly attract the label of opinion rather than fact. In its own summary C
the report states that its purpose is to establish whether the Hazard
D D
Assessment complies with the requirements of the SB and TM. The
E author gives his opinion on this issue. That question was the question the E
Director had to decide. It was his judgment call. Whether or not that
F F
decision was made at the time unlawfully or irrationally is for the court to
G determine. The answer to that question does not require a consideration G
of the subsequent competing opinions as to whether the 100% loss
H H
scenario is credible or not, whether a QRA on such a scenario is feasible or
I necessary or not, or whether the result of such a QRA, had it been done I
J
would have been acceptable or not. It does not constitute “true facts upon J
which the decision should have been made” nor does it contain matters
K K
which “the decision maker should have acquainted himself with, but did
L
not.” L
M M
45. Having applied the basic legal principles to the issue and
N having decided, as a result, that HSL is not admissible, further analysis of N
the report becomes unnecessary.
O O
P 46. Two final points require mention. Firstly, one of SWS’s P
arguments is that because no challenge was made to the Maclnnis report,
Q Q
which also post dates the Director’s decision, the respondent cannot now
R challenge other post decision material. I disagree for two reasons. As a R
statement of principle it is wrong. Simply because they did not challenge
S S
one report does not act as a waiver of a right to challenge subsequent
T reports. Also, the Maclnnis report did contain factual matters which were T
U U
V V
由此
- 23 -
A A
relevant to SWS’s original complaint as set out in their 13 July letter.
B B
Secondly, it was submitted at the preliminary hearing that the HSL report
C merely confirms and enlarges upon the Maclnnis report. Having now C
considered them both I think this understates the true position. I agree
D D
with Ms Li counsel for the Interested Party that a fairer reflection on the
E matter is that Maclnnis on its own, in the light of the AEAT and Shell E
reports could not establish that the Director’s decision was either unlawful
F F
or irrational. SWS therefore side-lined Maclnnis. HSL focused on the
G matter differently, namely on the failure to execute a QRA on the 100% G
loss scenario. SWS’s focus shifted accordingly.
H H
I THE CONSTRUCTION ARGUMENT I
J 47. I turn now to the competing submissions on how the EIAO is J
to be constructed in answer to the question — was it mandatory for the
K K
EIA report to contain a QRA on all hazards to life that had been identified?
L L
M 48. Where the meaning and effect of a statutory provision is the M
subject of legal argument the court should construe the provision
N N
purposively. The court’s interpretation should be consistent with the
O objects of the legislation as a whole. I have already set out what the dual O
objectives of the EIAO are. The key provisions which are under scrutiny
P P
are sections 6(1), 6(3), 8(3) and 10(2). They should be read together as
Q integral parts of an overall regime. Q
R R
49. Section 6(1) requires the EIA report to be “in accordance
S with” the SB and TM. Then, section 6(3) requires the Director to decide S
if the report “meets the requirements” of the SB and TM or not.
T T
U U
V V
由此
- 24 -
A A
50. The section 6(3) decision comes before sections 8 and 10. It
B B
is a decision to be made by the Director at a time when there is no public
C involvement. It has been argued by SWS that the whole EIA regime is a C
tripartite process involving the government, the developer and the public.
D D
In fact, the regime is not tripartite throughout. At the time the section 6(3)
E decision is made the first public window has closed (advertising the project E
profile) and the second public window has not yet opened (public
F F
comment on the signed EIA report).
G G
51. This is perhaps an appropriate moment to deal briefly with the
H H
complaint about the 25 April meeting, which immediately preceded the
I section 6(3) decision, at which it was decided that the 100% loss scenario I
J
did not warrant a QRA. It was suggested that this somehow J
circumvented public involvement. In my judgment this complaint does
K K
not stand up. The decision taken at the 25 April meeting was a
L
clarification of, not a dilution or variation of, the criteria. The EIAO L
provides that the report is prepared at a non public involvement stage in
M M
the regime. Any decision about its content will be without public
N consultation. The public consultation may later affect its approval but not N
its substance. After the section 6(3) decision the absence of a QRA on a
O O
100% loss scenario is open to debate and comment. In support of SWS’s
P case that an important part of the section 6(3) decision cannot be P
“surrendered to a private agreement” Mr Pleming cited two authorities
Q Q
from the UK (Gillespie v. First Secretary of State and Bellway Urban
R Renewal Southern [2003] EWCA Civ 400 and Smith v. Secretary of State R
for the Environment [2003] EWCA Civ 262.) Whilst these cases are
S S
instructive, their particular facts are wholly different and the UK statutory
T regime about which they are concerned is also very different. T
U U
V V
由此
- 25 -
A A
52. Like all decisions, section 6(3) requires judgment. Whether
B B
the answer is “Yes” or “No” does not depend on a robotic or check-list
C approach. Whether or not it “meets the requirements” of the SB and TM C
naturally depends on what the requirements of the SB and TM are. Those
D D
documents are not to be read as a strict list of things which must be done
E before it can be decided that its requirements have been met. It is now E
necessary to consider those two documents in a little detail.
F F
G The Study Brief G
H 53. Section 3.3.10 has been set out at page 16 of this judgment. H
The key parts are that when conducting a Hazard Assessment the applicant
I I
shall “follow the criteria for evaluating hazard to life as stated in
J Annexes 4 and 22 of the TM”. Included in the assessment is to be J
(a) identification of all hazard scenarios and (b) execution of a quantitative
K K
risk assessment.
L L
54. SWS submit that the TM must be followed rigidly and
M M
completely and that the word all in (a) should be read into (b) as well.
N N
O
55. I do not agree. O
P P
56. The SB requires an “assessment”. An assessment is defined
Q as “an evaluation or an estimate of the nature of”. A QRA is a tool to be Q
used in making the assessment. Section 3.3.10.1(ii) does not require a
R R
QRA for all hazardous scenarios. It is sufficient to execute a QRA for all
S those scenarios, which in the Director’s judgment, need to be addressed S
and assessed. Mr Yu points out that the next section of the SB,
T T
section 3.3.11 “Risk Assessment on Fuel Spillage” deals with the point
U U
V V
由此
- 26 -
A A
specifically. (i) says “identification of all fuel spillage scenarios … and
B B
(ii) says “quantification of the impacts … due to fuel spillage scenarios
C identified in (i)”. Section 3.3.10 could very easily have said the same C
thing but did not. Mr Haddon-Cave submits that sections 3.3.10 and
D D
3.3.11 differ because section 3.3.11 does not have the same preamble as
E section 3.3.10 (in which the TM is specifically mentioned). This is E
correct but, in my judgment, does not diminish the point that if all
F F
scenarios in section 3.3.10 had to be quantitatively assessed it would have
G said so. (The reliance on the TM as being the document which says that G
all hazards require a QRA is dealt with in the following section.)
H H
I 57. To require a QRA for all scenarios would include all I
J
incredible scenarios and scenarios which it is known will not occur. For J
illustrative purposes it is permissible to dip into the HSL report to support
K K
the Director’s decision that this cannot be the requirement. HSL accepts
L
that certain hazards can be eliminated qualitatively, such as those L
described as “boil over” and “brittle failure” because they have no possible
M M
relevance to this project in this location. Moreover, HSL does not explain
N why 100% instantaneous loss scenario could be a credible event. It does N
not answer the conclusions in the Shell and AEAT reports that it is not
O O
credible for a Jet A-l storage tank to split from top to bottom when one
P takes into account the actual design features and standards of construction P
and testing being applied in this particular project. In short, HSL says, it
Q Q
would be possible to do a QRA for the 100% loss scenario but does not go
R on to say that such a scenario is a credible event. R
S S
58. In the course of argument reference has been made to to
T SRAG — the UK Safety Report Assessment Guide. I refer to it to extract T
U U
V V
由此
- 27 -
A A
one passage only. The entire document has only a limited value in the
B B
present case because it relates to Potentially Hazardous Installations (PHIs)
C whereas the PAFF is not so designated and also it relates to “Highly C
Flammable Liquids” whereas Jet A-1 fuel in the PAFF is not classified as
D D
highly flammable. The passage which, in my judgment, describes a
E correct approach in our case is : E
F “Proportionality will influence the type and level of analysis F
detail that Assessors might expect to underpin the various
demonstrations in the safety report. …. It is important for
G G
Assessors to realise that QRA does not mean that a detailed and
full numerical analysis resulting in iso-risk contours and F/N
H societal risk curves is needed. Rather the extent of the H
quantification and the form it takes will depend on the site
specific circumstances determining the level of proportionality
I that applies.” I
J In other words, it is expected that the decision of expert assessors will be J
K
founded on professionalism and common sense. K
L L
59. SWS’s answer to the question — why should a QRA be done
M
for all scenarios is because the TM says so. I move on therefore to a M
consideration of the TM.
N N
O Technical Memorandum O
P
60. The first point to establish about the TM (and indeed, the SB P
also) is that it is not legislation. Section 16(12) of EIAO makes this
Q Q
clear :
R R
“16. Technical Memorandum ….
S (12) A technical memorandum is not subsidiary S
legislation.”
T T
U U
V V
由此
- 28 -
A A
61. Mr Pleming’s submission advances theories as to why that
B B
particular subsection may have been included. He submitted that at the
C very least the TM had legal effect. He said that the TM certainly looked C
like subsidiary legislation. In my judgment, the reason section 16(12)
D D
appears is plain. It is to put the matter beyond doubt lest anyone (here
E SWS) might think otherwise. E
F F
62. The fact that it is not subsidiary legislation provides the
G starting point for how it is to be treated. It is a guide. The TM itself, at G
paragraph 1.2.2 says so :
H H
“The Technical Memorandum on the Environmental Impact
I Assessment Process is a guide for the Director in deciding on I
matters under sections 5, 6, 8, 10, 12, 13 and 14 of the Ordinance.
J The Director is the Director of Environmental Protection. He J
will follow this technical memorandum as appropriate according
to the circumstances of a case.” (emphasis added)
K K
Words and phrases such as those emphasized do not appear in legislation.
L L
There are many other examples which illustrate that, whilst an important
M document, it provides for a degree of flexibility and common sense. It is M
not a straightjacket to be slavishly and mechanically followed, in which
N N
discretion and judgment play no part.
O O
63. Other examples of the language of the TM providing a pointer
P P
to how it should be used can be found in part 4 which sets out the criteria
Q for the EIA report. Q
R R
64. 4.1.1 states :
S S
“An EIA report shall comprise a document or series of
documents providing a detailed assessment in quantitative terms,
T T
wherever possible, and in qualitative terms of the likely
U U
V V
由此
- 29 -
A A
environmental impacts and environmental benefits of the project.
B The requirements for the EIA report shall be set out in B
accordance with this technical memorandum. The EIA report
shall be produced in accordance with the EIA study brief issued
C C
by the Director to the applicant.”
D D
65. SWS relies on the words “wherever possible”. They submit
E E
that as a QRA on the 100% loss scenario was possible (in support of which
F they rely on HSL) it should have been done. F
G G
66. However, this must be read in context. The whole sentence
H suggests that both quantitative and qualitative assessments will be done. H
They will be done in respect of the likely environmental impacts. The
I I
word “likely” appears in the next section also (objectives and contents of
J the report) : J
K “to identify and describe the elements of the community and K
environment likely to be affected by the proposed project(s),
and/or likely to cause adverse impacts to the proposed project(s),
L including both the natural and man-made environment and the L
associated environmental constraints;…” (emphasis added)
M M
N 67. The same section reminds the compiler of the report of the N
purposes and objectives of the report :
O O
“The contents of an EIA report shall fully meet the purposes and
P objectives set out in the EIA study brief issued by the Director, P
and shall adequately address all the issues set out in the EIA
study brief.”
Q Q
R 68. The general approaches and methodologies are set out in R
section 4.3. SWS point to 4.3.1(vi) :
S S
“predicting the likely nature, extent and magnitude of the
T anticipated changes and effects such that an evaluation, in T
U U
V V
由此
- 30 -
A A
quantitative terms as far as possible, can be made with respect to
B the criteria described in Annexes 4 to 10 inclusive.” (emphasis B
added)
C C
69. This should be read together with the section dealing with the
D D
review of the report (section 4.4) which again illustrates that the reviewer
E E
of the report is permitted to use his judgment subject to the guidance set
F
out : F
“Quality of the EIA Report: The quality of the EIA report shall
G G
be reviewed having regard to the guidelines in Annex 20 and in
Section 4.3. The report shall be considered as adequate if there
H are no omissions or deficiencies identified which may affect the H
results and conclusions of the assessment. …”
I I
70. Both counsel have helpfully referred the court to several
J J
authorities on the issue of the construction of the TM. I refer to just four
K and very briefly. The purpose is not to either follow or distinguish a K
particular decision but to borrow some apposite phrases which illustrate
L L
the correct approach to how the TM guide should be applied.
M M
N
71. R. v. Rochdale Metropolitan Borough Council ex parte Tew N
[1999] 3 PLR 74 was a planning case in which Sullivan J held that the
O O
regulation under discussion should be interpreted purposively rather than
P
literally : P
“ While regulation 3 of the applications regulations is
Q Q
expressed in mandatory terms — an application for planning
permission ‘shall’ include the particulars specified in the form
R provided by the local planning authority — I do not accept that R
failure to include one or more of those particulars means that the
application is invalid, so that the local planning authority is
S unable to grant planning permission even if it wishes to do so. S
The mandatory terms of regulation 3 are addressed to a practical
T problem and are intended to ensure that the local planning T
U U
V V
由此
- 31 -
A A
authority is able to require that certain particulars are provided as
B part of the application for planning permission. ….” B
C C
72. He later went on to say that to interpret in any other way
D would be “an unduly literal reading of the regulation”. D
E E
73. Similarly, the conclusions reached by Mackay J in R. v.
F Dorset County Council [2002] All ER (D) 68, another planning decision, F
are to point :
G G
“The adequacy of environmental information contained in an
H H
Environmental Statement is a matter for the judgement of the
planning authority, with which the Court will only interfere if it
I is proved to have been exercised irrationally. I
….
J J
It is not ‘every scrap of information’ which has to be
considered …. (a flexible attitude to compliance with a given
K K
paragraph’s requirement may be appropriate, ….
L I was not in the result persuaded by the decisions that Part II L
paragraphs 1, 2 and 3 have to be approached in the rather
mechanistic, sequential and discrete way contended for by
M Mr Fordham ….” (emphasis added) M
N N
74. The same theme is expressed by Jowitt J in R. v. Wakefield
O Metropolitan District Council ex parte Pearl Assurance plc (QBD) 1997 : O
The document under scrutiny was a planning policy guide (PPG).
P P
Jowitt J said :
Q Q
“…. PPGs are not delegated legislation and do not have the force
of statute. They are guidance and not tramlines. They do not
R R
purport to deal definitively with every situation which may
arise. ….
S S
…. Whether a piece of guidance amounts as a matter of law to a
material consideration has to be judged by reference to the
T content of the guidance seen in the factual context of the T
U U
V V
由此
- 32 -
A A
particular case. Moreover, there is an important distinction
B between having regard to guidance and being bound to follow B
it.” (emphasis added)
C C
and quoting Lord Hoffman from an earlier decision :
D D
“This distinction between whether something is a material
consideration and the weight which it should be given is only
E E
one aspect of a fundamental principle of British planning law,
namely that the courts are concerned only with the legality of the
F decision-making process and not with the merits of the decision. F
If there is one principle of planning law more firmly settled than
any other it is that matters of planning judgement are within the
G exclusive province of the local planning authority or the G
Secretary of State.”
H H
I 75. Adopting such an approach to the present case makes SWS’s I
task an uphill one. In my judgment, it is simply not sensible to extract the
J J
two words “wherever possible” from paragraph 4.1.1 of the TM and
K conclude that because HSL said that a QRA on the 100% loss scenario was K
“possible”, then the failure to carry it out renders the entire process
L L
unlawful. That would be “unduly literal”, “mechanistic” and not in
M accordance with the objectives and purposes of the ordinance. Rather, it M
should be read in its context in 4.1.1 which anticipates both quantitative
N N
and qualitative assessments as part of the guidance.
O O
76. Of course, this does not mean that the TM or any other similar
P P
guideline is to be treated in a cavalier way. It is to be applied responsibly
Q and with care, but not unduly literally and with blinkers. Failure to Q
comply with every requirement will not automatically render it invalid (as
R R
submitted by SWS). The court’s decision in the present case is that the
S particular non-compliance alleged is not to be construed as a S
non-compliance and thus the complaint that it was an invalid report fails in
T T
limine. What remains therefore is a possible challenge that the decision
U U
V V
由此
- 33 -
A A
not to assess the 100% instantaneous loss scenario quantitatively was
B B
Wednesbury unreasonable.
C C
Annex 4
D D
77. Before considering the case under “Wednesbury
E E
unreasonableness”, Annex 4 should not go unmentioned (although, absent
F HSL, its significance is diminished). Annex 4 provides the criteria for F
carrying out a QRA should it be deemed appropriate. Annex 4 states
G G
“The criterion for hazard to human life is to meet the Risk Guideline as
H shown in Figure 1. Figure 1 is in two parts : H
I (1) Individual risk guideline for acceptable risk levels. I
J
Maximum level of off site individual risk should not exceed J
one in 100,000 per year, i.e. 1 x 10-5/year.
K K
(2) Societal risk guidelines for acceptable risk levels.
L The societal risk is in the form of a graph. The horizontal L
axis is the number of fatalities (N) from one to 10,000. The
M M
vertical axis is the “frequency of accidents with N or more
N fatalities per year with one in a billion at the bottom and one N
in a hundred at the top. Roughly speaking the graph has
O three regions. If, statistically, a risk is in the top right hand O
region it is “unacceptable”, if it is the bottom left it is
P P
“acceptable”. If it is in a band between the two it is in the
Q “ALARP” region, namely “as low as reasonably practicable”. Q
This means that an ALARP risk should be mitigated to as low
R R
as reasonably practicable. The QRA done in the EIA report
was all in the “acceptable” region. HSL’s assessments
S S
entered into the ALARP region. Thus no risks, even those
T T
U U
V V
由此
- 34 -
A A
considered by HSL 10 months after the Director’s decision,
B B
were shown to be quantitatively unacceptable.
C C
D THE DIFFERENCES BETWEEN SWS’S CASE IN 2002 AND THE CASE D
NOW PRESENTED IN THIS JUDICIAL REVIEW HEARING
E E
78. As I have come to the conclusion that there are material
F differences between the case as first put and the case now, it is important F
to highlight those differences even though their primary relevance is
G G
towards the admissibility issue of the HSL report with which I have
H already dealt. It is useful however to contrast the two cases as a prelude H
to the next section which deals with each of the heads of challenge based
I I
on the information which was before the Director at the time of the
J decisions. J
K K
79. In the original notice of application it was stated that Jet A-1
L fuel was a “highly volatile substance”. The case was that the proximity of L
a storage depot of such a fuel to SWS’s steel mill posed an unacceptable
M M
risk because of the nature of the fuel and the nature of the works carried on
N N
in the mill and the number of people employed there. Leave to apply for
O
judicial review was granted on this basis. O
P P
80. In the case as now presented however, it is accepted that
Q Jet A-1 fuel is correctly categorized on “a flammable liquid” and not Q
highly volatile and that by complying with all safety requirements in the
R R
design, operating and testing of the PAFF it is safe in normal working
S conditions. The original focus of SWS’s case was addressed, in evidence, S
by an affirmation form Dr J. Wrigley, a Senior Environmental Protection
T T
U U
V V
由此
- 35 -
A A
Officer, in February 2003. That affirmation dealt exclusively with the
B B
case being advanced at that time. A summary of his evidence was :
C C
“HS/APG approved the Study Brief for the Hazard Assessment
which relates to risk to life. Other types of risk, such as
D personal injury or property damage are outside the scope of the D
Hazard Assessment (paras 6-9).
E E
The Hazard Assessment has been carefully reviewed by HS/APG
(para 10). The PAFF containment and drainage systems are key
F safety features which ensure that accidental spills of aviation fuel F
are contained on the PAFF site and then drain to sea (para 10v).
HS/APG advised EAND that the Hazard Assessment meets the
G requirements of the Study Brief and EIA TM from risk point of G
view (para 12).
H H
HS/APG and EAND have reviewed public comments including
SW comments on ignition sources at the Mill, ‘JW-2’. HS/APG
I conclude that ignition sources at the Mill have no impact or I
relevance to the Hazard Assessment due to adequate separation
distance between PAFF and the Mill (paras 13-18).”
J J
(HS/APG is Hazard Section of Air Policy Group).
K K
L L
81. The simple point is that virtually the entire focus of SWS’s
M
amended case, the 100% loss scenario, had not been mentioned. Mr Yu M
submits that had it been raised at the public consultation period it would
N N
have been considered and responded to in the same way as the concerns
O which were raised. O
P P
82. What is new is not the fact that no QRA was done but the
Q emergence of the issue that it should have been. Q
R R
83. In a recent 2nd affirmation Dr Wrigley reinforces the
S Director’s stance that, from the outset, the 100% loss scenario was S
regarded as incredible.
T T
U U
V V
由此
- 36 -
A A
“ ... when the Environmental Protection Department took the
B view that the Environmental Impact Assessment Report did not B
have to present a QRA on the instantaneous loss of 100% tank
content scenario, that was made on the basis that such an event
C C
was incredible. According to the experience that I and my team
have, it would not have made any difference to the risk
D assessment whether one attempts to set out some sort of D
quantitative assessment.
E Based on the meeting discussions, it was agreed that the E
‘100% instantaneous tank failure’ was incredible and could be
assessed qualitatively in the EIA. The ‘10% instantaneous tank
F F
failure’ was regarded as the worst credible event for the QRA
process, as explained in EIA para 10.5.2.8.”
G G
By implication therefore, we see that it was decided that by “all” was
H H
meant “all credible events” and by “credible” was meant all those from a
I realistic worst case scenario basis downwards. It was that decision which I
in my judgment cannot be impugned.
J J
K K
84. 10.5.2.8, which is a key passage in the report, is as follows :
L L
“The tank vapour space could be in the flammable range due
to vent opening to atmosphere and therefore ignition of tank
M vent due to lightning could result in a tank fire and M
subsequent failure at the roof to shell connection
(API 650 tanks are provided with a weak roof to shell
N N
connection which will fail preferentially to any other joint).
Such failures could also occur in the event of fire
O impingement to relieve excess vapours. It may be assumed O
that in the event of roof failure, the top most plate of the
shell connecting to the roof may also fail resulting in spill
P onto bund. Each plate is about 3m high which is about P
10% of the tank height. The catastrophic failure of the tank
Q is therefore assumed to result in a release of 10% of tank Q
contents (ie about 3,900 m3) on to the bund. Aircraft crash
is the only conceivable incident that can result in more than
R 10% of tank contents but this can be discounted, as the R
proposed site does not lie near to the flight path.”
S S
T T
U U
V V
由此
- 37 -
A A
SWS’s original case was based on the proximity of a highly volatile fuel
B B
farm. What remains is the proximity of a flammable liquid farm should
C an incredible event occur. C
D D
85. Another difference in SWS’s case is that, it now seeks to
E introduce a new ground of complaint based on the concept of “legitimate E
expectation”. The basis of the argument, in outline, is that as the EIA
F F
report was not in full and complete compliance with the requirements, the
G Director’s approval of it may have constituted an abuse of power. Put G
more mildly, if the Director did not understand the requirements that he
H H
had to comply with he misused his power in allowing it to be approved.
I I
J
86. I accept that this argument is not at the forefront of SWS’s J
case and that it is included not so much as a separate argument but within
K K
the principle that arguments based on unfairness, unreasonableness and
L
abuse of power can be intermingled (a note from Wade’s Administrative L
Law, 8th edition, p.385).
M M
N 87. It can nonetheless be answered shortly. The leading Hong N
Kong case of Ng Siu Tung v. Director of Immigration [2000] 5 HKCFAR 1
O O
deals comprehensively with the doctrine of legitimate expectation. In our
P case it has been advanced very late in the day, it was not in the notice of P
application, it is unsubstantiated and it falls outside the criteria in the Ng
Q Q
case, namely where :
R R
“... the legitimate expectation arose from a promise or
representation, the expectation being that the promise or
S representation would be honoured, should be properly taken into S
account in the decision-making process so long as to do so fell
within the power, statutory or otherwise, of the
T T
decision-maker ...”
U U
V V
由此
- 38 -
A A
It is difficult to understand what clear promise has been ignored in the
B B
present case in the context of the guidelines which the Director is required
C to follow in a non mechanistic and purposive manner. C
D D
WEDNESBURY UNREASONABLE?
E E
88. Having decided the issues of the “admissibility” of the HSL
F report and the “construction” issue in the respondent’s favour all that F
remains is to examine SWS’s six heads of complaint in the context of
G G
Wednesbury unreasonableness.
H H
89. The basic legal principles to be applied in each case are :
I I
(1) The court is not concerned with the correctness or otherwise
J J
of the decision.
K (2) The court will examine the unreasonableness (Wednesbury) K
on the basis of the material before the Director.
L L
(3) A challenge to the decision should be made promptly.
M M
(4) Remedies under judicial review are discretionary.
N N
(a) No QRA done on 100% loss scenari
O O
90. Having decided that neither TM nor the SB requires a QRA
P P
for every identified risk it cannot, in my judgment, be argued that a
Q decision not to do a QRA for an incredible scenario was unreasonable, let Q
alone Wednesbury unreasonable. The decision concerned technical
R R
matters, the report was compiled by experts, the Director was advised by
S experts. S
T T
U U
V V
由此
- 39 -
A A
91. To reach the high threshold at which a decision will be
B B
regarded as Wednesbury unreasonable is an uphill task for an applicant.
C As Sir Derek Cons VP in Nguyen Ho v. Director of Immigration [1991] 1 C
HKLR at p.583 put it :
D D
“I would most respectfully suggest that this approach must be in
E accordance with basic principles, for if the Court may properly E
interfere when the inferior tribunal has not taken into account
some matter which it should have done, the Court must also be
F F
able to do so when the inferior tribunal has got that matter wrong.
But it must be something that is plainly wrong or, as the judge
G below put it, ‘established unassailably to be erroneous’. Courts G
must in no circumstances allow themselves to be enticed into the
evaluation of a fact which is properly within the exclusive
H H
jurisdiction of the tribunal.”
I I
The appropriate test for the court to adopt is as stated by Keith J in Tran
J
Van Tien v. Director of Immigration (No.1) [1996] 7 HKPLR at p.177 : J
“... The test is not whether the evidence upon which the
K K
applicants seek to rely is capable of demonstrating that the facts
on which the decisions were based were plainly wrong. The
L test is whether the evidence demonstrated in fact that the facts on L
which the decisions were based were plainly wrong. …”
M M
In 1996, Lightman J in R. v. Director General of Telecommunications
N ex parte Cellcom (unreported) said : N
O “If (as I have stated) the Court should be very slow to impugn O
decisions of fact made by an expert and experienced
decision-maker, it must surely be even slower to impugn his
P P
educated prophesies and predictions for the future. ...
Q The Court may interfere with a decision if satisfied that the Q
Director has made a relevant mistake of fact or law. But a
mistake is not established by showing that on the material before
R the Director the Court would reach a different conclusion. The R
resolution of disputed questions of fact is for the decision-maker,
and the Court can only interfere if his decision is perverse eg if
S S
his reasoning is logically unsound. ... The Court may
interfere if the Director has taken into account an irrelevant
T consideration or has failed to take into account a relevant T
consideration. But so long as the Director takes a relevant
U U
V V
由此
- 40 -
A A
consideration into account, the weight to be given to that
B consideration and indeed whether any weight at all should be B
given to that consideration is a matter for the Director alone, so
long as his decision is not perverse: ...”
C C
In our case the attempt to impugn the Director’s decision is precisely as
D D
described by Laws J in R. v. Secretary of State for Transport ex parte
E
Richmond L.B.C. “a disguised through elegant plea upon the merits”. E
F F
92. With these principles in mind I turn to the remaining heads of
G G
challenge of which, as I have already found, none are truly free-standing
H
and all are closely linked to the “main” challenge. I have concluded that H
none of them can survive the fact that ground 1 has failed on all
I I
grounds — unlawfulness, unreasonableness and irrationality.
J J
(b) The material facts argument
K K
93. The facts known to the Director at the relevant time were that
L L
there was a steel mill next to the proposed site where approximately
M 300 workers worked in 2001 and that the number would be substantially M
the same in 2016. The precise distance of the mill boundaries and the
N N
PAFF were also known. The expert assessment, based on the hazards
O which were quantitatively assessed (i.e. all those that it was necessary to O
do) was that the risk to life was contained within the PAFF site.
P P
Q 94. I reject the argument that such a decision is rendered Q
Wednesbury reasonable, or invalid, by virtue of the decision maker’s
R R
failure to visit the steel mill and consider what goes on inside the mill.
S To be told that the steel mill contained molten metal, sparks, very high S
temperatures, many workers and frequent site traffic would not take
T T
U U
V V
由此
- 41 -
A A
anyone by surprise. Moreover, no survey of the mill was required by the
B B
SB and it is not suggested that the SB should have required one.
C C
(c) The applicant’s letter
D D
95. SWS’s case at trial is quite different from its case as set out in
E E
its 31 July 2003 letter. This particular ground can only have substance if
F it can be shown that the Director disregarded SWS’s concerns as set out in F
the letter. To be Wednesbury unreasonable the Director would have to be
G G
shown to have turned a blind eye to their proper concerns. The reality of
H the situation is that SWS’s complaint is not that their complaints were not H
addressed but that the Director disagreed with them. There is ample
I I
evidence that the concerns were addressed. The following are selected
J references to this issue from the affirmation evidence : J
K “… The comments discussed at that meeting included the K
concerns set out in Shiu Wing’s letter to the EIA Ordinance
Register Office dated 13 July 2002 referred to by Mr Pong at
L L
paragraph 6.8 of his Affirmation on behalf of Shiu Wing. The
main purpose of the meetings was for the Airport Authority, with
M its consultants, to show the EPD where in the EIA Report each M
comment was addressed. I and my colleagues, with our
consultants Mouchel and their sub-consultant, considered
N N
carefully all the comments raised, included Shui Wing’s concerns.
The EIA Report was considered to have covered all the
O comments.” (Mr W.O.W. Roberts, the Civil Engineering O
Manager for HKAA)
P P
“HS/APG have reviewed and commented on EAND response to
Q public comments including SW. There is now produced and Q
shown to me a copy of the comments marked exhibit ‘JW-2’.
I will now give further explanation of the important technical
R R
issues …” (Dr J. Wrigley)
S S
“During the public consultation period between 14 June 2002
and 14 July 2002, a total of 13 sets of comments were received
T T
by the EPD. The comments included comments from Shiu
U U
V V
由此
- 42 -
A A
Wing Steel Limited (‘SWS’) contained in a letter dated 13 July
B 2002… During this period, the public comments received were B
made available to the Secretary for the EIA Subcommittee
though there was no obligation on the part of EPD to do so. At
C C
the end of the consultation period, I conducted a preliminary
review of the comments and considered there were potentially
D major concerns expressed by the public. I therefore alerted all D
senior staff of the EPD including the Director, the Deputy
Director of Environmental Protection (‘Deputy Director’) and
E the Assistant Director of the concerns expressed, highlighting the E
major issues including those raised by SWS…
F F
After the public consultation period, staff of the EPD carried out
a thorough review of the issues raised by the public, collated
G them under different categories, discussed them with the HKAA G
and checked them against the EIA report. The staff of EPD
including myself were satisfied that the concerns appeared to
H H
have been fully addressed and, a set of detailed responses were
subsequently drafted …” (Mr Hui Yat Ming, a Principal
I Environmental Protection Officer) I
J J
(d) 25 April meeting
K K
96. This issue has been addressed earlier in this judgment. I do
L not consider there to be merit in the complaint that a decision was made L
behind closed doors and therefore to the disadvantages of the public. As
M M
already stated the EIA report is prepared in a “non public” period in the
N whole process. The basis of the risk assessment became public (namely N
the 10% loss of tank content scenario) and therefore open to scrutiny the
O O
moment the report was published. It is wrong to describe the Director as
P making a “belated admission” to this effect in August 2003. The P
consequence of the decision has been in the public domain since May 2002,
Q Q
and was affirmed to by Dr Wrigley in February 2003. Neither the TM
R nor the SB require disclosure of all the circumstances, considerations, R
deliberations and reasons which led up to any particular judgment or
S S
decision being made.
T T
U U
V V
由此
- 43 -
A A
97. In short it is suggested that because a decision concerning
B B
the content of the EIA report was made between the Director and the
C HKAA, (at the highest level and by acknowledged experts) at a time when C
there was no provision for public involvement, was Wednesbury
D D
unreasonable because it “surrendered the process to private agreement”.
E I consider this submission to be circular and illogical. E
F F
98. In any event, it is worthy to note that this complaint is not set
G out in SWS’s notice of application. The respondent and interested party G
have therefore not had an opportunity of filing evidence about it.
H H
I (e) Safeguards and conditions I
J 99. SWS’s complaint is that the Director has granted J
environmental approval and permission without ensuring that the full
K K
details of the project are fixed with certainty.
L L
100. Section 10(5) of the EIAO permits the granting of a permit
M M
with conditions. Section 9 makes the conditions enforceable and
N N
section 14 provides for the suspension of the project if the conditions are
O
not complied with. O
P P
101. SWS refers to an extract from Mr Hui Yat Ming’s affirmation
Q as the basis of the complaint : Q
“[w]here the particular [mitigation] measure is complex, difficult
R R
to express, or contain details not readily available during the EIA
stage, further submissions may be required to ensure that the
S project will be designed in line with the assumptions in the EIA S
while providing the necessary flexibility for minor project
changes.”
T T
U U
V V
由此
- 44 -
A A
102. It is argued that this amounts to an admission that the Director
B B
did not have sufficient information on which to base a decision that the
C qualitative assessment was sufficient and that the Director allowed HKAA C
to delay providing important technical information about the project.
D D
E 103. To interpret Mr Hui’s evidence in this way reads too much E
into it. No complaint can be made that the Director in acting in
F F
accordance with his powers acted unreasonably in the Wednesbury sense.
G That it could have been unlawful and outside his powers is unsustainable. G
H H
104. The role of conditions was considered and commented on in
I the “Long Valley” appeal : I
J “… Where a report is approved and permit granted, however, J
important steps in the process follow. These are:-
K K
a. The Director will often impose conditions on both the report
and the permit (see Schedule 4 of the Ordinance). These
L are to ensure (for example) that Habitat Creation and L
Maintenance Plans and Environmental Monitoring and Audit
Programmes outlined in the Report are later approved; that
M M
mitigation measures and the like are in place and satisfactory
before the project proceeds.
N N
b. The report will be placed in the register under section 8(5).
This is available for public inspection and if relevant may be
O relied upon for the granting of a permit for other projects O
without a further EIA study and report.
P P
c. The Director continues to monitor compliance before, during
and after construction and will if necessary use his
Q considerable powers under the enforcement provisions of the Q
Ordinance.
R There is a difference in emphasis between conditions to the R
approval of a report, which usually are to ensure that matters
dealt with in the report are completed. The Director’s approval
S S
of a Habitat Creation Plan for example. The conditions to a
permit are related to the construction work and are to ensure that
T the report is complied with before, during and after construction. T
U U
V V
由此
- 45 -
A A
For example a condition that a mitigation area is functioning
B before construction begins.” B
C Conditions enable matters of detail to be dealt with at a later stage. C
D D
105. Before I turn to the final section of this decision (namely the
E issue of discretion), I think it appropriate at this stage to deal briefly with E
an important point, hitherto unmentioned. The exhaustive EIA process,
F F
starting with the project profile, going through the SB, TM and report stage,
G on to the approval, permit and conditions stage is but one statutory control G
and safeguard in the construction of this important but sensitive installation.
H H
The Buildings Department, the Fire Services Department, the Marine
I Department and the Lands Department are others who exercise stringent I
statutory control over the project. The approval of the report and the
J J
granting of the permit under the EIAO is just one of a number of approvals
K K
to be sought. This court’s decision that the Director’s decision should not
L
be reviewed is one piece in a bigger picture. That is not to say that L
because there are other statutory schemes in place anything less than the
M M
highest standards of expertise and competence will do when the crucial
N decisions are made. It merely serves to show that these same tanks, bund N
wall, fuel properties and so on, will be scrutinized from a variety of
O O
different viewpoints.
P P
DISCRETION
Q Q
106. For the sake of completeness only, I make brief reference to
R R
the question of discretion. Remedies in judicial review are discretionary.
S In view of the decisions made I do not have to consider whether I should S
exercise a discretion not to grant any remedies even though a ground of
T T
judicial review has been made out.
U U
V V
由此
- 46 -
A A
107. However, had I found in favour of SWS on any one of the
B B
grounds of complaint, I address the issue of whether or not I would have
C exercised my discretion to decline to grant any relief. It would have been C
a difficult decision.
D D
E 108. At the end of the day I would have exercised the discretion in E
the Director’s favour. The outline reasons being :
F F
(a) that there was delay in commencing the proceedings. It is
G G
very arguable that the first decision which SWS submit was
H wrong was the section 6(3) decision. However no H
proceedings were commenced in relation to that decision
I I
although SWS’s original complaints plainly stem from the
content of the EIA report regardless of whether it was
J J
accepted or not. The section 6(3) decision was in June 2002,
K the section 8 and section 10 decisions were August. SWS’s K
letter of complaint had been in July but their original notice of
L L
application was not until 1 November 2002.
M (b) the crux of SWS’s case as presented at the hearing was largely M
technical in nature. It attacked the technical soundness of
N N
the EIA report based on expert opinion produced in the
O summer of 2003. Had the report been admitted and had the O
court decided a strict compliance with the letter of the TB and
P P
SB was required the outcome would have been that the
judicial review would have succeeded on the basis that it had
Q Q
been unlawful for the Director to carry a QRA on a scenario
R which was, based on the information available to the Director R
at the time, considered to be incredible.
S S
(c) In any event the case, as put in 2003, could have been made at
T the time of the public consultation but was not. T
U U
V V
由此
- 47 -
A A
(d) It is the court’s view that the sum of the evidence supports the
B B
submission that the same decision would be made now as was
C made in August 2002 notwithstanding the additional material C
which has been submitted.
D D
E 109. In short this court’s view would have been that the balancing E
exercise would have tilted in the respondent’s favour so that this particular
F F
major designated project would have been allowed to continue in the
G G
interest of the public at large and in the interest of good administration.
H H
110. All considerations concerning discretion are academic in view
I I
of the court’s primary conclusions.
J J
111. To conclude :
K K
(1) The Director’s decisions have been considered on the basis of
L the materials before him. L
M (2) SWS’s challenge that the decisions were unlawful based on M
the alleged failure to meet the requirements of the SB, the TM
N N
and the Ordinance have not been made out.
O (3) That challenge has been based, to a large extent, on the O
opinions in the HSL report which is inadmissible.
P P
(4) Were the post decision materials admissible they would have
Q resulted in a difference of expert opinion which itself would Q
not have altered the fact that the Director was acting within
R R
his power when he decided that the EIA report should be
approved as it complied with the SB and TM and that decision
S S
was not Wednesbury unreasonable.
T T
U U
V V
由此
- 48 -
A A
The answers to the five questions posed on pages 14 and 15 of this
B B
judgment are :
C C
(1) No.
D (2) Yes. D
E (3) Yes. E
(4) Not addressed as a separate issue.
F F
(5) Had the answers to (2) or (3) been different the discretion to,
G nonetheless, grant no relief would have been exercised. G
H H
112. This application is dismissed. The respondent’s and
I I
interested party’s costs are to be paid by the applicant.
J J
K K
L L
( M.P. Burrell )
M Judge of the Court of First Instance, M
High Court
N N
O O
Mr Charles Haddon-Cave, QC, Mr Nigel Pleming, QC and
Mr Anthony Chan, SC, instructed by Messrs Simmons & Simmons,
P P
for the Applicant
Q Mr Benjamin Yu, SC and Mr Anthony Ismail, instructed by Q
the Department of Justice, for the Respondent
R R
Ms Gladys Li, SC, instructed by Messrs Lovells, for the Interested Party
S S
T T
U U
V V
SHIU WING STEEL LTD v. DIRECTOR OF ENVIRONMENTAL PROTECTION
由此
A A
HCAL184/2002
B B
IN THE HIGH COURT OF THE
C HONG KONG SPECIAL ADMINISTRATIVE REGION C
COURT OF FIRST INSTANCE
D D
CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST
E NO.184 OF 2002 E
F --------------------- F
BETWEEN
G G
SHIU WING STEEL LIMITED Applicant
H H
I and I
J J
DIRECTOR OF ENVIRONMENTAL PROTECTION Respondent
K
AIRPORT AUTHORITY OF HONG KONG Interested Party K
L ---------------------- L
M Before : Hon Burrell J in Court M
Dates of Hearing : 5, 8-11, 15-17 September 2003
N N
Date of Judgment : 30 September 2003
O O
-------------------------
P JUDGMENT P
-------------------------
Q Q
1. The Hong Kong Airport Authority (“HKAA”) needs a new
R R
permanent air fuel farm (“PAFF”). During the late 1990’s many possible
S sites were considered. The result was that a site known as Tuen Mun 38 S
was chosen as the most suitable. Accordingly, they commenced the
T T
numerous procedures necessary to embark on such a project. If all the
U U
V V
由此
- 2 -
A A
procedures are successfully completed they have estimated that the PAFF
B B
would be operational by 2006.
C C
2. One of the many procedures is compliance with Cap.499, the
D D
Environmental Impact Assessment Ordinance (“EIAO”). The EIAO sets
E out a number of steps to be followed by the proposed developer. As part E
of their purported compliance with the EIAO the Director of
F F
Environmental Protection (“the Director”) has made decisions which have
G permitted the continuation of the project. Two of his decisions are now G
the subject of judicial review by the applicant (“SWS”) in these
H H
proceedings. The first decision was made on 2 August 2002. That was
I a decision to approve an EIA report submitted by the HKAA in relation to I
J
the PAFF for the Airport under section 8(3) of the EIAO. The second J
was on 28 August 2002. This was the decision under section 10(2) to
K K
grant an Environmental Permit with conditions (pursuant to section 10(5))
L
to the HKAA. L
M M
STATUTORY FRAMEWORK
N N
3. The EIAO is a relatively new, relatively short but very
O
important ordinance. It is clear from an overview of the whole enactment O
that it has a dual objective. The “overview” reveals a number of steps
P P
that a developer must take, each of them has a specified time limit. The
Q result is a fairly tight timetable to which both the developer and the Q
director must conform. The dual objectives strike a balance. The
R R
EIAO’s primary concern is the protection of the environment. Its
S framework provides a regime in which, and this is the second objective, S
important projects may be completed in a timely and efficient way,
T T
provided all the requirements of the EIAO are complied with. The
U U
V V
由此
- 3 -
A A
Tribunal’s report in the recent “Long Valley” appeal (KCR Corp. v.
B B
Director of Environmental Protection; EIA Appeal Board 2 of 2000)
C helpfully commented as follows : C
D “… The Ordinance gives the EIA process a legal structure. It is D
not a process which lies comfortably within a detailed legal
framework. Much of its success depends therefore upon the
E E
manner in which it is implemented within the outline structure
provided assisted by the Technical Memorandum. The
F consequence is that all involved are learning how best the F
various steps required can be implemented. … There are two
main matters of public interest involved. Both are important.
G The first is the public interest in the protection of the G
environment upon which the quality of life in Hong Kong will
H increasingly depend. The second is the public interest in H
ensuring that major designated projects are brought to fruition in
a timely and efficient manner. The time constraints put upon
I the Director for steps in the process and for his decisions show I
that the Ordinance aims to satisfy both interests.”
J J
K
4. The key provisions in the ordinance which demonstrate this K
step by step approach and dual objectives are these :
L L
(1) By section 4 certain projects (such as the PAFF) become
M “designated projects”. M
N (2) By section 5 the developer applies to the Director for a study N
brief (“SB”) and at the same time submits and advertises a
O project profile. The Director also informs the Advisory O
Council on the Environment (“ACE”). ACE is an
P P
independent advisory committee comprising 23 members. It
Q is a sort of watch-dog and is peculiar to Hong Kong in Q
environment impact regimes. ACE and the public have
R R
14 days within which it may comment on the project profile.
The Director must issue the SB within 45 days.
S S
(3) By section 6 HKAA prepares an EIA report in accordance
T T
with the SB (section 6(1)) and delivers it to the Director.
U U
V V
由此
- 4 -
A A
Within 60 days thereafter the Director decides if the report
B B
meets the requirements of the SB and the technical
C memorandum (“TM”) (section 6(3)). If he does, the report is C
then made available for a 30-day public inspection.
D D
(4) By section 7(5) ACE may give its comments within 60 days.
E E
(5) By section 8(3), within 30 days after the public inspection the
F
Director either approves, or approves conditionally or rejects F
the EIA report.
G G
(6) By section 10 HKAA may apply for the environmental permit
H for the project which the Director may grant (under H
section 10(2)).
I I
(7) By section 16 the Secretary for the Environment Transport
J and Works may issue TM setting out principles, procedures, J
guidelines, requirements and criteria for whether the EIA
K report meets the requirements of the SB. K
L L
5. In the present case SWS’s key complaint is that the Director’s
M M
decision to approve the report (section 8(3)) and grant the permit (section
N 10(2)) were either unlawful and/or Wednesbury unreasonable because the N
report did not meet the requirements of the SB and TM. SWS in this
O O
framework has no right of appeal against the Director’s decision. Only a
P party to the project itself has such a right. The SB and the TM are key P
documents. The TM is the framework of criteria out of which an SB is
Q Q
created. The SB is the template of objectives and obligations against
R which the EIA report is prepared. They will both be considered in more R
detail later in this judgment.
S S
T T
U U
V V
由此
- 5 -
A A
BACKGROUND
B B
6. The background to the issues in this judicial review is best
C C
understood by reference to a chronology of key events.
D D
7. In April 2001 HKAA applied with a project profile for an SB.
E E
On 31 May 2001 the Director issued the SB and HKAA engaged Mouchel
F to prepare the EIA report (in June 2001). The report took nearly a year to F
produce. It is 480 pages long. The “Hazard to Life” section, with which
G G
this judicial review is concerned, runs to 55 pages.
H H
8. The report was submitted to the Director for his consideration
I I
under section 6 on 3 May 2002. It had been signed as a complete report
J on 26 April 2002. The day before, 25 April, an important meeting had J
taken place between representatives of the Director and HKAA. At this
K K
meeting a decision was made that one of the particular hazards to life that
L the report had identified, namely an instantaneous loss of 100% of the L
contents of a fuel tank, need not be quantitatively assessed. It was
M M
decided that it was sufficient to assess such a scenario qualitatively. This
N N
decision lies at the heart of this judicial review.
O O
9. In short, a quantitative assessment requires a statistical
P P
analysis. It results in a numerical representation of the likelihood of
Q deaths occurring from a particular type of accident occurring and at what Q
frequency and in what numbers. A qualitative analysis, on the other hand,
R R
is more subjective. It does not require an input of statistical data. It is
S an assessment made by experts in the field. It is the report’s failure to S
carry out a quantitative assessment (“QRA”) of the 100% instant loss
T T
scenario upon which SWS relies as the lynchpin to their case. They
U U
V V
由此
- 6 -
A A
submit that failure rendered the report deficient so that the Director’s
B B
approval of it was unlawful.
C C
10. During May, June and July the various provisions of the
D D
EIAO were complied with. The report entered the public domain. SWS
E wrote its letter of complaint on 13 July 2002. The key extracts from that E
letter, which summarize SWS’s opposition to the project which pre-date
F F
the Director’s decision are as follows :
G G
“‘… SWS believes that the EIA report on the proposed PAFF has
not addressed adequately the impact of the PAFF on the Mill as
H H
an existing user of a high temperature operation.’
I ‘Spillage I
The effects of a major spillage incident on water at both the
J Castle Peak Power Station in the proximity and the Mill would J
be catastrophic. Both facilities use seawater intakes for
cool-down process, but no reference is made in the EIA report as
K K
to how the location of the jetty, the discharge of the fuel and
anchoring of tankers will affect these. Besides, the impact of an
L oil spill on adjacent industries have not been considered in L
respect of the seawater intake.’
M ‘Risk of Fire M
In the EIA report, several references are made to the potential
N N
emissions from both the transfer (working losses) and storage
(standing storage losses) of the aviation fuel. Yet the total
O volume of the likely emissions is not discussed. The more O
important shortcoming is that the EIA Report has not made
references to the fact that the Mill is sited immediately adjacent
P to the proposed PAFF and will engage in processes which P
o
involve very high temperatures (up to 1300 C). The siting of a
Q facility which discharges aviation fuel vapours immediately Q
adjacent to a facility of very high temperature processes and
furnace operations is unsafe. In this case, any spillage incident
R would be catastrophic.’” R
S S
T T
U U
V V
由此
- 7 -
A A
11. ACE met to consider the report and all public comments on
B B
29 July 2002. It declared that it was satisfied that the risk was within
C acceptable levels and endorsed the report. C
D D
12. On 2 August 2002 the Director approved the report under
E section 8(3). The section 10(2) permit was granted on 28 August, with E
conditions.
F F
G 13. At some stage during this process SWS had commissioned its G
own report. That report (the “Maclnnis” report) is dated 16 October 2002.
H H
It was sent to the Director on 21 October. The accompanying letter
I summarizes the report’s conclusions as follows : I
J “(1) The EIA Report does not meet the requirements of the J
Technical Memorandum.
K K
(2) All reasonable hazardous scenarios have not been
considered, and certain assumptions/methodologies used in
L the EIA are questionable and/or inaccurate. L
(3) Construction of the Proposed PAFF at Area 38 may produce
M hazardous conditions that would result in a greater hazard M
to life than intended by the EIA Ordinance.
N N
The points raised have been put to the Town Planning Board and
the Airport Authority. Given the nature of the risks Shiu Wing
O have decided that it would be in the interest of all concerned to O
make the report available in its entirety. The Airport Authority
have been asked to confirm that it has thought of these risks and
P P
that it has adequate measures in place to safeguard safety.
Q Safety Q
As stated above, this is obviously a very special situation, and
R strict compliance with all required procedure and technical R
memoranda is vital. Shiu Wing have no wish to be obstructive,
but we clearly have a major interest in the outcome of your
S decision. The Macinnis Report confirms that the proximity of S
the Steel Mill’s operations is not discussed in the EIA report but
T may be of importance if there was a fuel spill inside or outside T
the bund area, and that there are a number of possible ignition
U U
V V
由此
- 8 -
A A
sources which have not been considered. In all the
B circumstances, you should not hesitate to suspend, vary or cancel B
the permit if you are in any doubt regarding the information
previously provided, or the safety of the project.
C C
Notwithstanding the importance of the project, we would suggest
that you cannot be too cautious in these circumstances.”
D D
E 14. After a brief exchange of correspondence between the various E
parties SWS issued its notice of application for judicial review on
F F
1 November 2002. Leave was granted by Hartmann J on 13 November.
G G
15. Since the granting of leave further reports from all sides have
H H
been prepared. In response to Maclnnis the HKAA filed a report by AEA
I Technology (“AEAT report”) on 5 February 2003, and the Director filed a I
report from Shell Global Solutions (“Shell”) on 12 February. AEAT
J J
concluded that :
K K
“(a) None of the issues raised by Macinnis identify errors or
omissions in the EIA Report which AEAT consider would
L significantly affect the predicted risk levels, which lie L
within the acceptable region of the criteria established in
M Annex 4 of the Technical Memorandum; … M
(d) AEAT consider that the EIA Report identifies and discusses
N all reasonable hazardous scenarios associated with the N
PAFF. In particular, AEAT do not consider it was
necessary for the EIA Report to consider specifically the
O O
scenarios suggested by Macinnis in which : (a) hot
surfaces within the Steel Mill could ignite a release from
P the PAFF; (b) smoke carrying inflammable vapours could P
ignite on reaching the Steel Mill; and (c) hot gases emitted
from the Steel Mill could lead to ignition of Jet A-1 at the
Q PAFF. AEAT consider that these potential scenarios are Q
reasonably covered within the general scenarios adopted
R by the EIA Report; and R
(e) AEAT consider that the assumptions and methodologies
S used in the EIA Report are reasonable within the scope of S
the assessment. In particular, AEAT consider that the
thermal impact criterion used in the EIA Report is a
T T
reasonable approximation for the PAFF, which will not
U U
V V
由此
- 9 -
A A
significantly affect the predicted risk levels compared
B with the criteria established in Annex 4 of the Technical B
Memorandum, when compared to other reasonable
calculation methods.’
C C
Based on this review, AEAT consider that none of the issues
D identified by Macinnis would change the key conclusion in D
paragraph 10.9.7 of the EIA Report, namely that ‘Based on the
analysis presented in this section, including the
E recommendations, it can be concluded that the offsite individual E
and societal risks posed by the activities at the PAFF tank farm
and associated marine environment are acceptable according to
F F
the criteria set out in Annex 4 of the EIAO-TM (ie the Technical
Memorandum).”
G G
H 16. Shell concluded that : H
I “The EIA for the PAFF at Tuen Mun Area 38 has been I
challenged for not taking sufficient account of the neighbouring
Shiu Wing Steel Mill. Although the presence of the mill and its
J workforce is specifically mentioned, Macinnis claim that the J
effect modelling described in the EIA is not sufficiently
K conservative, and that worse case scenarios deemed incredible by K
the authors of the EIA should have been included.
L It has been shown in this report that the extra scenarios L
mentioned by Macinnis are indeed incredible, and that the
scenarios and assumptions in the EIA Report are comprehensive
M M
and robust. The worst-case scenario addressed in the EIA (tank
overfill) is the worst foreseeable, and was modelled
N conservatively in that the assumed damage was significantly N
worse than is observed in practice. The hazard to life
assessment in the EIA remains sufficient, and retains its validity.
O O
Even if the extra hypothetical scenarios postulated by Macinnis
P
after the EIA was published were to be included as a sensitivity
P
study, they do not pose a risk to the people in the steel mill or to
its structure, and the total risk for the PAFF is still acceptable.”
Q Q
R 17. SWS were clearly not satisfied with these conclusions. As a R
result, their notice of application was re-amended and a further report
S S
filed — the “HSL” report (Health & Safety Laboratory, a much respected
T T
U U
V V
由此
- 10 -
A A
UK organization) written by Mr Marc McBride. A summary of that
B B
report’s findings are :
C C
(1) The Hazard Assessment is fundamentally flawed because it
D fails to identify and assess the risk associated with a D
catastrophic failure of one of the aviation fuel storage tanks,
E E
i.e. instantaneous loss of 100% of the tank contents. This is
contrary to common practice for Hazard Assessment studies
F F
in Hong Kong and published international good practice.
G Furthermore, there have been past occurrences of catastrophic G
tank failure relevant to the PAFF.
H H
(2) The Hazard Assessment fails to comply with the requirements
I of the EIA Study Brief because it does not identify all I
hazardous scenarios, in particular the catastrophic tank failure
J J
scenario.
K (3) HSL’s assessment is that this scenario could cause almost K
200 fatalities at the SWS site, due to the significant fraction of
L L
aviation fuel which would overtop the bund (as demonstrated
M by theoretical models, large scale experimental studies and M
past incidents), together with the strong likelihood of ignition
N N
associated with activities at the steel plant.
O (4) The Hazard Assessment grossly underestimates the risk O
associated with the proposed PAFF. Using the figure
P P
contained in section 10.5.2 of the Hazard Assessment on the
frequency of catastrophic tank failure, the overall risk for the
Q Q
PAFF (2040 case) is calculated to lie with the upper ‘ALARP’
R region of the Risk Guidelines, rather than in the “acceptable” R
region as the EIA report would suppose (ALARP stands for
S S
As Low As Reasonably Practicable).
T T
U U
V V
由此
- 11 -
A A
(5) There is a significant off-site risk associated with the
B B
proposed PAFF. Compliance only with minimum separation
C distances does not provide an acceptable basis for the siting of C
the PAFF. Good practice would require that the decision as
D D
to its siting be risk-based, having regard to the location and
E surroundings of the installation, irrespective of separation E
distances.
F F
(6) The proposed PAFF design does not comply with relevant
G international standards, namely the Institute of Petroleum G
Model Code of Safe Practice, Part 2 : Design, Construction
H H
and Operation of Distribution Facilities.
I I
SWS acknowledge that (1) and (2) are inaccurate. The EIA report did
J identify the 100% instantaneous loss scenario and it did assess it. What it J
did not do is assess it quantitatively. The report had concluded that the
K K
worst case scenario was a 10% loss when it said “The catastrophic failure
L of the tank is therefore assumed to result in a release of 10% of tank L
contents (i.e. about 3,900 m3) on to the bund”.
M M
N 18. There is no complaint that the assessment of the “10% worst N
case scenario” was not fully addressed in considerable detail in the report.
O O
The conclusion that the QRA be confined to the 10% scenario is preceded
P by a wealth of scientific data. P
Q Q
19. I have set out the conclusions to these reports for two reasons.
R Firstly, to demonstrate one of the few things about which there is R
agreement between the parties in this case, namely that there is a
S S
difference of opinion between the experts. (In passing, it is also agreed
T that the scientific or technical debate between the experts cannot be and is T
U U
V V
由此
- 12 -
A A
not to be resolved by the court. The parties are unanimous that the court
B B
should not get involved with the debate between the experts). Secondly,
C the filing of these reports (together with two affirmations on behalf of C
SWS from Mr T. Maylor and Libor Rostik which provide, inter alia,
D D
evidence about the workings of the steel mill) prompted a preliminary
E hearing which was heard in this court on 24 July 2003 in which SWS E
applied for leave to re-amend the notice of application and file the HSL
F F
report and the two affirmations. The application was opposed. At the
G end of a relatively short hearing, which only scratched the surface of the G
issues and the reports, I granted leave to re-amend and admitted the fresh
H H
evidence relied on by SWS de bene esse. One reason for admitting it
I de bene esse was to give the court an opportunity at the full hearing to I
J
consider the report and its relevance in greater depth. This has now J
happened and I consider the matter more fully later in this judgment.
K K
L
20. Throughout the above events, many affirmations and L
affidavits have been filed. 12 deponents have filed 18 affirmations
M M
totalling 177 pages.
N N
THE ISSUES
O O
21. SWS on the one hand and the Director and HKAA on the
P P
other do not agree what the issues to be resolved by the court are. The
Q prime reasons for the disagreement are that : Q
R
(a) there is no consensus as to the legal boundaries set by judicial R
review proceedings. SWS submit they are changing and
S widening, S
T T
U U
V V
由此
- 13 -
A A
(b) the admissibility of the HSL report remains an issue.
B B
Without it the issues are narrower.
C C
D 22. Defining the issues is a highly significant exercise. In some D
ways it goes a long way towards determining the outcome of the judicial
E E
review itself.
F F
23. Erring on the safe side all counsel have addressed the court on
G G
all issues, that is, those advanced by SWS. Counsel’s submissions have
H been comprehensive. Mr Charles Haddon-Cave, QC and H
Mr Nigel Pleming, QC leading Mr Anthony Chan, SC have appeared for
I I
SWS. The Director has been represented by Mr Benjamin Yu, SC
J leading Mr Anthony Ismail and Ms Gladys Li, SC has represented HKAA. J
Their instructive and helpful skeleton submissions run to 250 pages. The
K K
research of all three legal teams has been impressive. Whether the court
L proceeds therefore on the wide list of issues contended for by SWS or the L
more conservative list proposed by the Director is a very important
M M
decision. Mr Haddon-Cave’s list of issues and consequential issues pose
N 24 questions to be answered. Mr Yu lists five issues. N
O O
24. As will be seen from what follows in this judgment, and after
P anxious deliberation, I have preferred the narrower approach submitted by P
the respondent and HKAA. I will not, therefore, set out all the issues as
Q Q
advanced by SWS. Mr Pleming, an acknowledged and respected expert
R in administrative law commenced his submissions as follows : R
S “ This is, I hope your Lordship will accept, a very important S
case for environmental law in Hong Kong. Your Lordship’s
T
judgment will no doubt significantly assist in a number of ways, T
apart from assisting the particular parties.
U U
V V
由此
- 14 -
A A
Could I respectfully suggest what those ways might be.
B First of all, it will be the first opportunity for the court in Hong B
Kong to express its view as to the meaning, if it has a view, and
can express one, on the language and the purpose -- and
C C
I emphasise the purpose -- of the ordinance and the technical
memorandum.
D D
The second area of significance is that your Lordship’s
judgment will provide an opportunity for the determination of
E the true role and expectations of the public. By ‘the public’ E
I also include the advisory council as the representative of the
public, in what Mr Haddon-Cave has described so far as, and
F F
I here add as part of my submissions, a tripartite process.
G The third area of importance is that your Lordship’s G
judgment may be a step in the direction of determining the
standards to be applied in the approval process. I cover by that
H all stages in the ordinance, from compliance through approval to H
permit, the degree of rigidity or laxity that is involved.”
I I
J 25. The view of this court is that first instance judgments should J
be primarily, if not solely, directed towards the decision which the parties
K K
want to know. Should that decision necessitate matters of statutory
L construction or applications of principle then so be it. However, such L
determinations should be confined to only those which are necessary for
M M
the court to carry out its primary task which in this case is to apply the
N Hong Kong law of judicial review to the two decisions under challenge N
and decide if any grounds have been made out to review them.
O O
P 26. It seems to me therefore that the respondent’s issues better P
reflect the task of this court in this case. They are :
Q Q
(1) Whether the evidence in the form of expert reports are
R R
admissible in judicial review proceedings by way of exception
S under R. v. Secretary of State for the Environment ex parte S
Powis [1981] 1 WLR 584?
T T
U U
V V
由此
- 15 -
A A
(2) Whether the Director acted lawfully in approving the EIA
B B
report and allowing the project proponent not to carry out a
C quantitative risk assessment on instantaneous release of 100% C
of a tank content?
D D
(3) Whether the Director acted reasonably in the public law sense
E in approving the EIA report and allowing the project E
proponent not to carry out a quantitative risk assessment on
F F
instantaneous release of 100% of a tank content?
G (4) Whether the challenge that the EIA report does not comply G
with the SB and the TM is out of time?
H H
(5) Whether the court in the exercise of discretion should grant
I relief having regard to : I
J (a) delay; J
(b) prejudice to the Airport Authority;
K K
(c) prejudice to good administration.
L L
M 27. It will be noted that the first issue concerns the admissibility M
of the HSL report. I therefore deal with this as a preliminary issue next.
N N
Before doing so I should add that SWS’s list of issues has not been
O shredded. On the contrary, they remain a useful guide to structure this O
judgment. The 24 questions have been helpfully grouped under the
P P
six heads of challenge contained in the re-amended notice of application.
Q I propose to deal with each of those challenges separately, although in Q
many instances, briefly. Before, therefore, I turn to the important
R R
question of the admissibility of the HSL report, it is convenient to set out,
S in summary form, SWS’s six heads of challenge. S
T T
U U
V V
由此
- 16 -
A A
SWS’S GROUNDS OF CHALLENGE
B B
28. SWS’s case is that the EIA report is deficient in that it failed
C C
to comply with the legal requirement of EIAO, in particular the
D requirements of the SB or TM. If that proposition is correct the D
Director’s approval of it, under section 8(3) was unlawful because it was
E E
not a proper or valid report under section 6. For the same reason the
F section 10(2) permit was not lawfully granted either. F
G G
29. Six separate grounds are identified. In truth, grounds 2 to 6
H flow from ground 1. Ground 1 is the crux of the matter. Ground 1 H
depends on how the ordinance is construed. Counsel for SWS
I I
acknowledge that there is considerable overlap between the various
J grounds. In spite of submissions to the contrary I am not persuaded that J
any of grounds 2 to 6 can be freestanding.
K K
(a) Ground 1 is described as the Quantitative Risk Assessment
L L
argument (“the QRA argument”). Paragraph 3.3.10 of the
M SB states : M
“3.3.10 Hazard To Life
N N
3.3.10.1 The risk to the life, including the workers of nearby
plants, due to marine transport, jetty transfer, tank farm
O storage and pipeline transfer of aviation fuel shall be O
assessed. The Applicant shall follow the criteria for
P
evaluating hazard to life as stated in Annexes 4 and 22 P
of the TM in conducting hazard assessment and
include the following in the assessment:
Q Q
(i) identification of all hazardous scenarios associated
with the marine transport, jetty transfer, tank farm
R storage and pipeline transfer of aviation fuel, which R
may cause fatalities;
S (ii) execution of a Quantitative Risk Assessment S
expressing population risks in both individual and
societal term;
T T
U U
V V
由此
- 17 -
A A
(iii) comparison of individual and societal risks with the
B Criteria for Evaluating Hazard to Life stipulated in B
Annex 4 of the TM; and
C (iv) identification and assessment of practicable and cost C
effective risk mitigation measures as appropriate.”
D D
In short, having identified a 100% instantaneous loss as a
E E
scenario under (i), they were required to execute a QRA in
F respect of it. Once identified the TM required that a QRA F
must be done in respect of all identified hazards.
G G
(b) Ground 2 is described as the Material Facts argument. It is
H submitted that prior to making his decision the Director failed H
to acquaint himself with the nature of the works at the steel
I mill and the number of people who worked there. I
J (c) Ground 3 is the Applicant’s letter argument. It is submitted J
that the Director disregarded SWS’s letter of complaint dated
K K
13 July 2002.
L (d) Ground 4 is the 25 April 2002 meeting argument. The L
decision not to carry out a QRA in respect of 100%
M M
instantaneous loss was taken at a meeting between the
Director and HKAA just prior to releasing the report. It is
N N
submitted that the effect of this decision was to remove a key
O issue, namely 100% catastrophic failure, from public debate O
and consideration.
P P
(e) Ground 5 is the Safeguards argument. It is submitted that
Q the Director should not have relied on the various safeguards Q
that were incorporated into the design and operation of the
R R
PAFF when deciding not to do a QRA for the 100% loss
S scenario. S
(f) Finally ground 6 is the Conditions argument. It is submitted
T T
that a condition which was imposed on the granting of the
U U
V V
由此
- 18 -
A A
permit (“Permit Condition 3.9”) was unlawful as it fell
B B
outside Schedule 4 of the EIAO.
C C
D 30. Before considering these grounds in more detail, I now turn to D
the preliminary issue of the admissibility of the HSL report.
E E
F THE HSL REPORT — ADMISSIBILITY F
G 31. The quality and expertise of the HSL report, together with G
independence and excellent reputation of HSL itself is not doubted.
H H
I 32. The report has been admitted de bene esse. The court has I
now had a full opportunity (as opposed to a superficial opportunity at the
J J
preliminary hearing on 23 July) to consider the purpose and content of the
K report in the light of issues to be determined. K
L L
33. Counsel for SWS submit that the report and the fresh
M evidence is admissible as an exception to the general rule. Authorities M
and learned texts have been cited in support of the general proposition that
N N
the circumstances in which post decision materials can be admitted is
O widening. Bearing in mind the importance and complexity of this case, it O
is submitted that the court should lean in favour of including it rather than
P P
excluding it.
Q Q
34. The general rule can be found in R. v. Secretary of State for
R R
the Environment ex parte Powis [1981] 1 WLR at p.595 :
S S
“Finally there was an application on behalf of the tenant to admit
fresh evidence which the Divisional Court had refused to admit.
T T
Like the Divisional Court we considered the evidence de bene
U U
V V
由此
- 19 -
A A
esse. What are the principles on which fresh evidence should
B be admitted on judicial review? They are (1) that the court can B
receive evidence to show what material was before the minister
or inferior tribunal : … (2) where the jurisdiction of the minister
C C
or inferior tribunal depends on a question of fact or where the
question is whether essential procedural requirements were
D observed, the court may receive and consider additional evidence D
to determine the jurisdictional fact or procedural error : … and
(3) where the proceedings are tainted by misconduct on the part
E of the minister or member of the inferior tribunal or the parties E
before it. Examples of such misconduct are bias by the
F decision making body, or fraud or perjury by a party. In each F
case fresh evidence is admissible to prove the particular
misconduct alleged : …”
G G
H
35. There are many examples of the application of the general H
rule in Hong Kong. For example in Nguyen Ho v. Director of
I I
Immigration [1991] 1 HKLR 576, Cons VP said :
J J
“From that exposition alone I am satisfied that unreasonableness
as a factor by itself, what might be termed the second limb in
K Wednesbury, can only be judged with regard to what was known K
to the inferior tribunal at the time.”
L L
36. In Yu Chee Yin v. Commissioner of ICAC [2001] 2 HKC 91 at
M M
104, Hartmann J said :
N N
“It is common cause that the evidence contained in the
affirmations was not before the Commissioner when he made his
O decision. Indeed, that is the foundation of the applicant’s O
third challenge. But a claim of unreasonableness in the
P ‘Wednesbury’ sense is judged in light of the information that was P
before the decision maker when he made the decision. It is not
judged in the light of information that has only become known
Q after the event.” Q
R R
37. SWS submits there are four reasons to treat the HSL report as
S an exception to the general rule. I consider it sufficient to simply recite S
T T
U U
V V
由此
- 20 -
A A
those four reasons without reviewing the many authorities to which I was
B B
referred in the course of submissions.
C C
38. First, where it is alleged that the decision maker failed to take
D D
account of a relevant fact, evidence can be admitted to show (a) why it is
E relevant and (b) the significance of the disregarded material in the E
decision-making process.
F F
G 39. Second, this case falls within the second head of Powis : G
Where the jurisdiction of the decision maker depends on a question of fact
H H
evidence is admissible to challenge the fact and to show that he had no
I jurisdiction or authority to do what he did. I
J J
40. Third, there is an “emerging” category for admission of
K K
material not before the decision-maker. Where a decision is made in
L
ignorance of or contrary to the true facts, evidence is admissible to L
demonstrate the true facts upon which the decision should have been based,
M M
provided that it is shown that the facts placed before or found by the
N decision maker were “plainly wrong”. N
O O
41. Fourth, where it is alleged that the defendant has failed in its
P duty to acquaint itself with relevant information, it will often be essential P
for the applicant to demonstrate (in a case such as this by reference to both
Q Q
factual and expert evidence) that there was material with which the
R decision maker should have been acquainted at the time of the relevant R
decisions but was not. Here, that category covers the true factual
S S
situation at the steel mill described by Maylor and Rostik.
T T
U U
V V
由此
- 21 -
A A
42. In short it is argued that HSL establishes that a QRA on the
B B
100% loss scenario could have been carried out, but was not, and had it
C been the Director’s decision could have been different. C
D D
43. I have considered the authorities relied on by SWS and in
E particular the passage from Fordham Administrative Law under the E
heading “Fresh evidence in Judicial Review”. For the reasons which
F F
follow I have come to the conclusion that the report is not admissible
G because the grounds for categorizing it as an admissible exception to the G
general rule have not been made out. Any apparent inconsistencies
H H
between the reasons for excluding it now and the reasons for admitting it
I de bene esse on 23 July stem, quite simply, from the full nature of the I
J
argument in this hearing compared with the brief nature of the argument in J
the former hearing. It is worth mentioning also that SWS’s primary
K K
argument, namely that the section 8(3) decision was unlawful because the
L
EIA report was deficient is a question of construction and remains in tact L
with or without HSL.
M M
N 44. I agree with the general argument advanced by the Director N
and HKAA that, in reality, the HSL report is an expert opinion in support
O O
of SWS’s latest case (I deal later with the point that SWS’s latest case is
P significantly different from its original case upon which leave for judicial P
review was granted). As such, it merely reinforces the undoubted truth
Q Q
that expert opinions differ. The fact that a QRA was not being done on
R the 100% loss scenario was known from 3 May 2002. The alleged R
deficiency, which is the crux of the HSL report, could have been placed
S S
before the Director before he made his decision but was not. SWS submit,
T as they must do, that the report contains fact not opinion which should T
U U
V V
由此
- 22 -
A A
have been before the Director. To separate fact from opinion in this
B B
particular report is almost impossible. Taken as a whole its conclusions
C plainly attract the label of opinion rather than fact. In its own summary C
the report states that its purpose is to establish whether the Hazard
D D
Assessment complies with the requirements of the SB and TM. The
E author gives his opinion on this issue. That question was the question the E
Director had to decide. It was his judgment call. Whether or not that
F F
decision was made at the time unlawfully or irrationally is for the court to
G determine. The answer to that question does not require a consideration G
of the subsequent competing opinions as to whether the 100% loss
H H
scenario is credible or not, whether a QRA on such a scenario is feasible or
I necessary or not, or whether the result of such a QRA, had it been done I
J
would have been acceptable or not. It does not constitute “true facts upon J
which the decision should have been made” nor does it contain matters
K K
which “the decision maker should have acquainted himself with, but did
L
not.” L
M M
45. Having applied the basic legal principles to the issue and
N having decided, as a result, that HSL is not admissible, further analysis of N
the report becomes unnecessary.
O O
P 46. Two final points require mention. Firstly, one of SWS’s P
arguments is that because no challenge was made to the Maclnnis report,
Q Q
which also post dates the Director’s decision, the respondent cannot now
R challenge other post decision material. I disagree for two reasons. As a R
statement of principle it is wrong. Simply because they did not challenge
S S
one report does not act as a waiver of a right to challenge subsequent
T reports. Also, the Maclnnis report did contain factual matters which were T
U U
V V
由此
- 23 -
A A
relevant to SWS’s original complaint as set out in their 13 July letter.
B B
Secondly, it was submitted at the preliminary hearing that the HSL report
C merely confirms and enlarges upon the Maclnnis report. Having now C
considered them both I think this understates the true position. I agree
D D
with Ms Li counsel for the Interested Party that a fairer reflection on the
E matter is that Maclnnis on its own, in the light of the AEAT and Shell E
reports could not establish that the Director’s decision was either unlawful
F F
or irrational. SWS therefore side-lined Maclnnis. HSL focused on the
G matter differently, namely on the failure to execute a QRA on the 100% G
loss scenario. SWS’s focus shifted accordingly.
H H
I THE CONSTRUCTION ARGUMENT I
J 47. I turn now to the competing submissions on how the EIAO is J
to be constructed in answer to the question — was it mandatory for the
K K
EIA report to contain a QRA on all hazards to life that had been identified?
L L
M 48. Where the meaning and effect of a statutory provision is the M
subject of legal argument the court should construe the provision
N N
purposively. The court’s interpretation should be consistent with the
O objects of the legislation as a whole. I have already set out what the dual O
objectives of the EIAO are. The key provisions which are under scrutiny
P P
are sections 6(1), 6(3), 8(3) and 10(2). They should be read together as
Q integral parts of an overall regime. Q
R R
49. Section 6(1) requires the EIA report to be “in accordance
S with” the SB and TM. Then, section 6(3) requires the Director to decide S
if the report “meets the requirements” of the SB and TM or not.
T T
U U
V V
由此
- 24 -
A A
50. The section 6(3) decision comes before sections 8 and 10. It
B B
is a decision to be made by the Director at a time when there is no public
C involvement. It has been argued by SWS that the whole EIA regime is a C
tripartite process involving the government, the developer and the public.
D D
In fact, the regime is not tripartite throughout. At the time the section 6(3)
E decision is made the first public window has closed (advertising the project E
profile) and the second public window has not yet opened (public
F F
comment on the signed EIA report).
G G
51. This is perhaps an appropriate moment to deal briefly with the
H H
complaint about the 25 April meeting, which immediately preceded the
I section 6(3) decision, at which it was decided that the 100% loss scenario I
J
did not warrant a QRA. It was suggested that this somehow J
circumvented public involvement. In my judgment this complaint does
K K
not stand up. The decision taken at the 25 April meeting was a
L
clarification of, not a dilution or variation of, the criteria. The EIAO L
provides that the report is prepared at a non public involvement stage in
M M
the regime. Any decision about its content will be without public
N consultation. The public consultation may later affect its approval but not N
its substance. After the section 6(3) decision the absence of a QRA on a
O O
100% loss scenario is open to debate and comment. In support of SWS’s
P case that an important part of the section 6(3) decision cannot be P
“surrendered to a private agreement” Mr Pleming cited two authorities
Q Q
from the UK (Gillespie v. First Secretary of State and Bellway Urban
R Renewal Southern [2003] EWCA Civ 400 and Smith v. Secretary of State R
for the Environment [2003] EWCA Civ 262.) Whilst these cases are
S S
instructive, their particular facts are wholly different and the UK statutory
T regime about which they are concerned is also very different. T
U U
V V
由此
- 25 -
A A
52. Like all decisions, section 6(3) requires judgment. Whether
B B
the answer is “Yes” or “No” does not depend on a robotic or check-list
C approach. Whether or not it “meets the requirements” of the SB and TM C
naturally depends on what the requirements of the SB and TM are. Those
D D
documents are not to be read as a strict list of things which must be done
E before it can be decided that its requirements have been met. It is now E
necessary to consider those two documents in a little detail.
F F
G The Study Brief G
H 53. Section 3.3.10 has been set out at page 16 of this judgment. H
The key parts are that when conducting a Hazard Assessment the applicant
I I
shall “follow the criteria for evaluating hazard to life as stated in
J Annexes 4 and 22 of the TM”. Included in the assessment is to be J
(a) identification of all hazard scenarios and (b) execution of a quantitative
K K
risk assessment.
L L
54. SWS submit that the TM must be followed rigidly and
M M
completely and that the word all in (a) should be read into (b) as well.
N N
O
55. I do not agree. O
P P
56. The SB requires an “assessment”. An assessment is defined
Q as “an evaluation or an estimate of the nature of”. A QRA is a tool to be Q
used in making the assessment. Section 3.3.10.1(ii) does not require a
R R
QRA for all hazardous scenarios. It is sufficient to execute a QRA for all
S those scenarios, which in the Director’s judgment, need to be addressed S
and assessed. Mr Yu points out that the next section of the SB,
T T
section 3.3.11 “Risk Assessment on Fuel Spillage” deals with the point
U U
V V
由此
- 26 -
A A
specifically. (i) says “identification of all fuel spillage scenarios … and
B B
(ii) says “quantification of the impacts … due to fuel spillage scenarios
C identified in (i)”. Section 3.3.10 could very easily have said the same C
thing but did not. Mr Haddon-Cave submits that sections 3.3.10 and
D D
3.3.11 differ because section 3.3.11 does not have the same preamble as
E section 3.3.10 (in which the TM is specifically mentioned). This is E
correct but, in my judgment, does not diminish the point that if all
F F
scenarios in section 3.3.10 had to be quantitatively assessed it would have
G said so. (The reliance on the TM as being the document which says that G
all hazards require a QRA is dealt with in the following section.)
H H
I 57. To require a QRA for all scenarios would include all I
J
incredible scenarios and scenarios which it is known will not occur. For J
illustrative purposes it is permissible to dip into the HSL report to support
K K
the Director’s decision that this cannot be the requirement. HSL accepts
L
that certain hazards can be eliminated qualitatively, such as those L
described as “boil over” and “brittle failure” because they have no possible
M M
relevance to this project in this location. Moreover, HSL does not explain
N why 100% instantaneous loss scenario could be a credible event. It does N
not answer the conclusions in the Shell and AEAT reports that it is not
O O
credible for a Jet A-l storage tank to split from top to bottom when one
P takes into account the actual design features and standards of construction P
and testing being applied in this particular project. In short, HSL says, it
Q Q
would be possible to do a QRA for the 100% loss scenario but does not go
R on to say that such a scenario is a credible event. R
S S
58. In the course of argument reference has been made to to
T SRAG — the UK Safety Report Assessment Guide. I refer to it to extract T
U U
V V
由此
- 27 -
A A
one passage only. The entire document has only a limited value in the
B B
present case because it relates to Potentially Hazardous Installations (PHIs)
C whereas the PAFF is not so designated and also it relates to “Highly C
Flammable Liquids” whereas Jet A-1 fuel in the PAFF is not classified as
D D
highly flammable. The passage which, in my judgment, describes a
E correct approach in our case is : E
F “Proportionality will influence the type and level of analysis F
detail that Assessors might expect to underpin the various
demonstrations in the safety report. …. It is important for
G G
Assessors to realise that QRA does not mean that a detailed and
full numerical analysis resulting in iso-risk contours and F/N
H societal risk curves is needed. Rather the extent of the H
quantification and the form it takes will depend on the site
specific circumstances determining the level of proportionality
I that applies.” I
J In other words, it is expected that the decision of expert assessors will be J
K
founded on professionalism and common sense. K
L L
59. SWS’s answer to the question — why should a QRA be done
M
for all scenarios is because the TM says so. I move on therefore to a M
consideration of the TM.
N N
O Technical Memorandum O
P
60. The first point to establish about the TM (and indeed, the SB P
also) is that it is not legislation. Section 16(12) of EIAO makes this
Q Q
clear :
R R
“16. Technical Memorandum ….
S (12) A technical memorandum is not subsidiary S
legislation.”
T T
U U
V V
由此
- 28 -
A A
61. Mr Pleming’s submission advances theories as to why that
B B
particular subsection may have been included. He submitted that at the
C very least the TM had legal effect. He said that the TM certainly looked C
like subsidiary legislation. In my judgment, the reason section 16(12)
D D
appears is plain. It is to put the matter beyond doubt lest anyone (here
E SWS) might think otherwise. E
F F
62. The fact that it is not subsidiary legislation provides the
G starting point for how it is to be treated. It is a guide. The TM itself, at G
paragraph 1.2.2 says so :
H H
“The Technical Memorandum on the Environmental Impact
I Assessment Process is a guide for the Director in deciding on I
matters under sections 5, 6, 8, 10, 12, 13 and 14 of the Ordinance.
J The Director is the Director of Environmental Protection. He J
will follow this technical memorandum as appropriate according
to the circumstances of a case.” (emphasis added)
K K
Words and phrases such as those emphasized do not appear in legislation.
L L
There are many other examples which illustrate that, whilst an important
M document, it provides for a degree of flexibility and common sense. It is M
not a straightjacket to be slavishly and mechanically followed, in which
N N
discretion and judgment play no part.
O O
63. Other examples of the language of the TM providing a pointer
P P
to how it should be used can be found in part 4 which sets out the criteria
Q for the EIA report. Q
R R
64. 4.1.1 states :
S S
“An EIA report shall comprise a document or series of
documents providing a detailed assessment in quantitative terms,
T T
wherever possible, and in qualitative terms of the likely
U U
V V
由此
- 29 -
A A
environmental impacts and environmental benefits of the project.
B The requirements for the EIA report shall be set out in B
accordance with this technical memorandum. The EIA report
shall be produced in accordance with the EIA study brief issued
C C
by the Director to the applicant.”
D D
65. SWS relies on the words “wherever possible”. They submit
E E
that as a QRA on the 100% loss scenario was possible (in support of which
F they rely on HSL) it should have been done. F
G G
66. However, this must be read in context. The whole sentence
H suggests that both quantitative and qualitative assessments will be done. H
They will be done in respect of the likely environmental impacts. The
I I
word “likely” appears in the next section also (objectives and contents of
J the report) : J
K “to identify and describe the elements of the community and K
environment likely to be affected by the proposed project(s),
and/or likely to cause adverse impacts to the proposed project(s),
L including both the natural and man-made environment and the L
associated environmental constraints;…” (emphasis added)
M M
N 67. The same section reminds the compiler of the report of the N
purposes and objectives of the report :
O O
“The contents of an EIA report shall fully meet the purposes and
P objectives set out in the EIA study brief issued by the Director, P
and shall adequately address all the issues set out in the EIA
study brief.”
Q Q
R 68. The general approaches and methodologies are set out in R
section 4.3. SWS point to 4.3.1(vi) :
S S
“predicting the likely nature, extent and magnitude of the
T anticipated changes and effects such that an evaluation, in T
U U
V V
由此
- 30 -
A A
quantitative terms as far as possible, can be made with respect to
B the criteria described in Annexes 4 to 10 inclusive.” (emphasis B
added)
C C
69. This should be read together with the section dealing with the
D D
review of the report (section 4.4) which again illustrates that the reviewer
E E
of the report is permitted to use his judgment subject to the guidance set
F
out : F
“Quality of the EIA Report: The quality of the EIA report shall
G G
be reviewed having regard to the guidelines in Annex 20 and in
Section 4.3. The report shall be considered as adequate if there
H are no omissions or deficiencies identified which may affect the H
results and conclusions of the assessment. …”
I I
70. Both counsel have helpfully referred the court to several
J J
authorities on the issue of the construction of the TM. I refer to just four
K and very briefly. The purpose is not to either follow or distinguish a K
particular decision but to borrow some apposite phrases which illustrate
L L
the correct approach to how the TM guide should be applied.
M M
N
71. R. v. Rochdale Metropolitan Borough Council ex parte Tew N
[1999] 3 PLR 74 was a planning case in which Sullivan J held that the
O O
regulation under discussion should be interpreted purposively rather than
P
literally : P
“ While regulation 3 of the applications regulations is
Q Q
expressed in mandatory terms — an application for planning
permission ‘shall’ include the particulars specified in the form
R provided by the local planning authority — I do not accept that R
failure to include one or more of those particulars means that the
application is invalid, so that the local planning authority is
S unable to grant planning permission even if it wishes to do so. S
The mandatory terms of regulation 3 are addressed to a practical
T problem and are intended to ensure that the local planning T
U U
V V
由此
- 31 -
A A
authority is able to require that certain particulars are provided as
B part of the application for planning permission. ….” B
C C
72. He later went on to say that to interpret in any other way
D would be “an unduly literal reading of the regulation”. D
E E
73. Similarly, the conclusions reached by Mackay J in R. v.
F Dorset County Council [2002] All ER (D) 68, another planning decision, F
are to point :
G G
“The adequacy of environmental information contained in an
H H
Environmental Statement is a matter for the judgement of the
planning authority, with which the Court will only interfere if it
I is proved to have been exercised irrationally. I
….
J J
It is not ‘every scrap of information’ which has to be
considered …. (a flexible attitude to compliance with a given
K K
paragraph’s requirement may be appropriate, ….
L I was not in the result persuaded by the decisions that Part II L
paragraphs 1, 2 and 3 have to be approached in the rather
mechanistic, sequential and discrete way contended for by
M Mr Fordham ….” (emphasis added) M
N N
74. The same theme is expressed by Jowitt J in R. v. Wakefield
O Metropolitan District Council ex parte Pearl Assurance plc (QBD) 1997 : O
The document under scrutiny was a planning policy guide (PPG).
P P
Jowitt J said :
Q Q
“…. PPGs are not delegated legislation and do not have the force
of statute. They are guidance and not tramlines. They do not
R R
purport to deal definitively with every situation which may
arise. ….
S S
…. Whether a piece of guidance amounts as a matter of law to a
material consideration has to be judged by reference to the
T content of the guidance seen in the factual context of the T
U U
V V
由此
- 32 -
A A
particular case. Moreover, there is an important distinction
B between having regard to guidance and being bound to follow B
it.” (emphasis added)
C C
and quoting Lord Hoffman from an earlier decision :
D D
“This distinction between whether something is a material
consideration and the weight which it should be given is only
E E
one aspect of a fundamental principle of British planning law,
namely that the courts are concerned only with the legality of the
F decision-making process and not with the merits of the decision. F
If there is one principle of planning law more firmly settled than
any other it is that matters of planning judgement are within the
G exclusive province of the local planning authority or the G
Secretary of State.”
H H
I 75. Adopting such an approach to the present case makes SWS’s I
task an uphill one. In my judgment, it is simply not sensible to extract the
J J
two words “wherever possible” from paragraph 4.1.1 of the TM and
K conclude that because HSL said that a QRA on the 100% loss scenario was K
“possible”, then the failure to carry it out renders the entire process
L L
unlawful. That would be “unduly literal”, “mechanistic” and not in
M accordance with the objectives and purposes of the ordinance. Rather, it M
should be read in its context in 4.1.1 which anticipates both quantitative
N N
and qualitative assessments as part of the guidance.
O O
76. Of course, this does not mean that the TM or any other similar
P P
guideline is to be treated in a cavalier way. It is to be applied responsibly
Q and with care, but not unduly literally and with blinkers. Failure to Q
comply with every requirement will not automatically render it invalid (as
R R
submitted by SWS). The court’s decision in the present case is that the
S particular non-compliance alleged is not to be construed as a S
non-compliance and thus the complaint that it was an invalid report fails in
T T
limine. What remains therefore is a possible challenge that the decision
U U
V V
由此
- 33 -
A A
not to assess the 100% instantaneous loss scenario quantitatively was
B B
Wednesbury unreasonable.
C C
Annex 4
D D
77. Before considering the case under “Wednesbury
E E
unreasonableness”, Annex 4 should not go unmentioned (although, absent
F HSL, its significance is diminished). Annex 4 provides the criteria for F
carrying out a QRA should it be deemed appropriate. Annex 4 states
G G
“The criterion for hazard to human life is to meet the Risk Guideline as
H shown in Figure 1. Figure 1 is in two parts : H
I (1) Individual risk guideline for acceptable risk levels. I
J
Maximum level of off site individual risk should not exceed J
one in 100,000 per year, i.e. 1 x 10-5/year.
K K
(2) Societal risk guidelines for acceptable risk levels.
L The societal risk is in the form of a graph. The horizontal L
axis is the number of fatalities (N) from one to 10,000. The
M M
vertical axis is the “frequency of accidents with N or more
N fatalities per year with one in a billion at the bottom and one N
in a hundred at the top. Roughly speaking the graph has
O three regions. If, statistically, a risk is in the top right hand O
region it is “unacceptable”, if it is the bottom left it is
P P
“acceptable”. If it is in a band between the two it is in the
Q “ALARP” region, namely “as low as reasonably practicable”. Q
This means that an ALARP risk should be mitigated to as low
R R
as reasonably practicable. The QRA done in the EIA report
was all in the “acceptable” region. HSL’s assessments
S S
entered into the ALARP region. Thus no risks, even those
T T
U U
V V
由此
- 34 -
A A
considered by HSL 10 months after the Director’s decision,
B B
were shown to be quantitatively unacceptable.
C C
D THE DIFFERENCES BETWEEN SWS’S CASE IN 2002 AND THE CASE D
NOW PRESENTED IN THIS JUDICIAL REVIEW HEARING
E E
78. As I have come to the conclusion that there are material
F differences between the case as first put and the case now, it is important F
to highlight those differences even though their primary relevance is
G G
towards the admissibility issue of the HSL report with which I have
H already dealt. It is useful however to contrast the two cases as a prelude H
to the next section which deals with each of the heads of challenge based
I I
on the information which was before the Director at the time of the
J decisions. J
K K
79. In the original notice of application it was stated that Jet A-1
L fuel was a “highly volatile substance”. The case was that the proximity of L
a storage depot of such a fuel to SWS’s steel mill posed an unacceptable
M M
risk because of the nature of the fuel and the nature of the works carried on
N N
in the mill and the number of people employed there. Leave to apply for
O
judicial review was granted on this basis. O
P P
80. In the case as now presented however, it is accepted that
Q Jet A-1 fuel is correctly categorized on “a flammable liquid” and not Q
highly volatile and that by complying with all safety requirements in the
R R
design, operating and testing of the PAFF it is safe in normal working
S conditions. The original focus of SWS’s case was addressed, in evidence, S
by an affirmation form Dr J. Wrigley, a Senior Environmental Protection
T T
U U
V V
由此
- 35 -
A A
Officer, in February 2003. That affirmation dealt exclusively with the
B B
case being advanced at that time. A summary of his evidence was :
C C
“HS/APG approved the Study Brief for the Hazard Assessment
which relates to risk to life. Other types of risk, such as
D personal injury or property damage are outside the scope of the D
Hazard Assessment (paras 6-9).
E E
The Hazard Assessment has been carefully reviewed by HS/APG
(para 10). The PAFF containment and drainage systems are key
F safety features which ensure that accidental spills of aviation fuel F
are contained on the PAFF site and then drain to sea (para 10v).
HS/APG advised EAND that the Hazard Assessment meets the
G requirements of the Study Brief and EIA TM from risk point of G
view (para 12).
H H
HS/APG and EAND have reviewed public comments including
SW comments on ignition sources at the Mill, ‘JW-2’. HS/APG
I conclude that ignition sources at the Mill have no impact or I
relevance to the Hazard Assessment due to adequate separation
distance between PAFF and the Mill (paras 13-18).”
J J
(HS/APG is Hazard Section of Air Policy Group).
K K
L L
81. The simple point is that virtually the entire focus of SWS’s
M
amended case, the 100% loss scenario, had not been mentioned. Mr Yu M
submits that had it been raised at the public consultation period it would
N N
have been considered and responded to in the same way as the concerns
O which were raised. O
P P
82. What is new is not the fact that no QRA was done but the
Q emergence of the issue that it should have been. Q
R R
83. In a recent 2nd affirmation Dr Wrigley reinforces the
S Director’s stance that, from the outset, the 100% loss scenario was S
regarded as incredible.
T T
U U
V V
由此
- 36 -
A A
“ ... when the Environmental Protection Department took the
B view that the Environmental Impact Assessment Report did not B
have to present a QRA on the instantaneous loss of 100% tank
content scenario, that was made on the basis that such an event
C C
was incredible. According to the experience that I and my team
have, it would not have made any difference to the risk
D assessment whether one attempts to set out some sort of D
quantitative assessment.
E Based on the meeting discussions, it was agreed that the E
‘100% instantaneous tank failure’ was incredible and could be
assessed qualitatively in the EIA. The ‘10% instantaneous tank
F F
failure’ was regarded as the worst credible event for the QRA
process, as explained in EIA para 10.5.2.8.”
G G
By implication therefore, we see that it was decided that by “all” was
H H
meant “all credible events” and by “credible” was meant all those from a
I realistic worst case scenario basis downwards. It was that decision which I
in my judgment cannot be impugned.
J J
K K
84. 10.5.2.8, which is a key passage in the report, is as follows :
L L
“The tank vapour space could be in the flammable range due
to vent opening to atmosphere and therefore ignition of tank
M vent due to lightning could result in a tank fire and M
subsequent failure at the roof to shell connection
(API 650 tanks are provided with a weak roof to shell
N N
connection which will fail preferentially to any other joint).
Such failures could also occur in the event of fire
O impingement to relieve excess vapours. It may be assumed O
that in the event of roof failure, the top most plate of the
shell connecting to the roof may also fail resulting in spill
P onto bund. Each plate is about 3m high which is about P
10% of the tank height. The catastrophic failure of the tank
Q is therefore assumed to result in a release of 10% of tank Q
contents (ie about 3,900 m3) on to the bund. Aircraft crash
is the only conceivable incident that can result in more than
R 10% of tank contents but this can be discounted, as the R
proposed site does not lie near to the flight path.”
S S
T T
U U
V V
由此
- 37 -
A A
SWS’s original case was based on the proximity of a highly volatile fuel
B B
farm. What remains is the proximity of a flammable liquid farm should
C an incredible event occur. C
D D
85. Another difference in SWS’s case is that, it now seeks to
E introduce a new ground of complaint based on the concept of “legitimate E
expectation”. The basis of the argument, in outline, is that as the EIA
F F
report was not in full and complete compliance with the requirements, the
G Director’s approval of it may have constituted an abuse of power. Put G
more mildly, if the Director did not understand the requirements that he
H H
had to comply with he misused his power in allowing it to be approved.
I I
J
86. I accept that this argument is not at the forefront of SWS’s J
case and that it is included not so much as a separate argument but within
K K
the principle that arguments based on unfairness, unreasonableness and
L
abuse of power can be intermingled (a note from Wade’s Administrative L
Law, 8th edition, p.385).
M M
N 87. It can nonetheless be answered shortly. The leading Hong N
Kong case of Ng Siu Tung v. Director of Immigration [2000] 5 HKCFAR 1
O O
deals comprehensively with the doctrine of legitimate expectation. In our
P case it has been advanced very late in the day, it was not in the notice of P
application, it is unsubstantiated and it falls outside the criteria in the Ng
Q Q
case, namely where :
R R
“... the legitimate expectation arose from a promise or
representation, the expectation being that the promise or
S representation would be honoured, should be properly taken into S
account in the decision-making process so long as to do so fell
within the power, statutory or otherwise, of the
T T
decision-maker ...”
U U
V V
由此
- 38 -
A A
It is difficult to understand what clear promise has been ignored in the
B B
present case in the context of the guidelines which the Director is required
C to follow in a non mechanistic and purposive manner. C
D D
WEDNESBURY UNREASONABLE?
E E
88. Having decided the issues of the “admissibility” of the HSL
F report and the “construction” issue in the respondent’s favour all that F
remains is to examine SWS’s six heads of complaint in the context of
G G
Wednesbury unreasonableness.
H H
89. The basic legal principles to be applied in each case are :
I I
(1) The court is not concerned with the correctness or otherwise
J J
of the decision.
K (2) The court will examine the unreasonableness (Wednesbury) K
on the basis of the material before the Director.
L L
(3) A challenge to the decision should be made promptly.
M M
(4) Remedies under judicial review are discretionary.
N N
(a) No QRA done on 100% loss scenari
O O
90. Having decided that neither TM nor the SB requires a QRA
P P
for every identified risk it cannot, in my judgment, be argued that a
Q decision not to do a QRA for an incredible scenario was unreasonable, let Q
alone Wednesbury unreasonable. The decision concerned technical
R R
matters, the report was compiled by experts, the Director was advised by
S experts. S
T T
U U
V V
由此
- 39 -
A A
91. To reach the high threshold at which a decision will be
B B
regarded as Wednesbury unreasonable is an uphill task for an applicant.
C As Sir Derek Cons VP in Nguyen Ho v. Director of Immigration [1991] 1 C
HKLR at p.583 put it :
D D
“I would most respectfully suggest that this approach must be in
E accordance with basic principles, for if the Court may properly E
interfere when the inferior tribunal has not taken into account
some matter which it should have done, the Court must also be
F F
able to do so when the inferior tribunal has got that matter wrong.
But it must be something that is plainly wrong or, as the judge
G below put it, ‘established unassailably to be erroneous’. Courts G
must in no circumstances allow themselves to be enticed into the
evaluation of a fact which is properly within the exclusive
H H
jurisdiction of the tribunal.”
I I
The appropriate test for the court to adopt is as stated by Keith J in Tran
J
Van Tien v. Director of Immigration (No.1) [1996] 7 HKPLR at p.177 : J
“... The test is not whether the evidence upon which the
K K
applicants seek to rely is capable of demonstrating that the facts
on which the decisions were based were plainly wrong. The
L test is whether the evidence demonstrated in fact that the facts on L
which the decisions were based were plainly wrong. …”
M M
In 1996, Lightman J in R. v. Director General of Telecommunications
N ex parte Cellcom (unreported) said : N
O “If (as I have stated) the Court should be very slow to impugn O
decisions of fact made by an expert and experienced
decision-maker, it must surely be even slower to impugn his
P P
educated prophesies and predictions for the future. ...
Q The Court may interfere with a decision if satisfied that the Q
Director has made a relevant mistake of fact or law. But a
mistake is not established by showing that on the material before
R the Director the Court would reach a different conclusion. The R
resolution of disputed questions of fact is for the decision-maker,
and the Court can only interfere if his decision is perverse eg if
S S
his reasoning is logically unsound. ... The Court may
interfere if the Director has taken into account an irrelevant
T consideration or has failed to take into account a relevant T
consideration. But so long as the Director takes a relevant
U U
V V
由此
- 40 -
A A
consideration into account, the weight to be given to that
B consideration and indeed whether any weight at all should be B
given to that consideration is a matter for the Director alone, so
long as his decision is not perverse: ...”
C C
In our case the attempt to impugn the Director’s decision is precisely as
D D
described by Laws J in R. v. Secretary of State for Transport ex parte
E
Richmond L.B.C. “a disguised through elegant plea upon the merits”. E
F F
92. With these principles in mind I turn to the remaining heads of
G G
challenge of which, as I have already found, none are truly free-standing
H
and all are closely linked to the “main” challenge. I have concluded that H
none of them can survive the fact that ground 1 has failed on all
I I
grounds — unlawfulness, unreasonableness and irrationality.
J J
(b) The material facts argument
K K
93. The facts known to the Director at the relevant time were that
L L
there was a steel mill next to the proposed site where approximately
M 300 workers worked in 2001 and that the number would be substantially M
the same in 2016. The precise distance of the mill boundaries and the
N N
PAFF were also known. The expert assessment, based on the hazards
O which were quantitatively assessed (i.e. all those that it was necessary to O
do) was that the risk to life was contained within the PAFF site.
P P
Q 94. I reject the argument that such a decision is rendered Q
Wednesbury reasonable, or invalid, by virtue of the decision maker’s
R R
failure to visit the steel mill and consider what goes on inside the mill.
S To be told that the steel mill contained molten metal, sparks, very high S
temperatures, many workers and frequent site traffic would not take
T T
U U
V V
由此
- 41 -
A A
anyone by surprise. Moreover, no survey of the mill was required by the
B B
SB and it is not suggested that the SB should have required one.
C C
(c) The applicant’s letter
D D
95. SWS’s case at trial is quite different from its case as set out in
E E
its 31 July 2003 letter. This particular ground can only have substance if
F it can be shown that the Director disregarded SWS’s concerns as set out in F
the letter. To be Wednesbury unreasonable the Director would have to be
G G
shown to have turned a blind eye to their proper concerns. The reality of
H the situation is that SWS’s complaint is not that their complaints were not H
addressed but that the Director disagreed with them. There is ample
I I
evidence that the concerns were addressed. The following are selected
J references to this issue from the affirmation evidence : J
K “… The comments discussed at that meeting included the K
concerns set out in Shiu Wing’s letter to the EIA Ordinance
Register Office dated 13 July 2002 referred to by Mr Pong at
L L
paragraph 6.8 of his Affirmation on behalf of Shiu Wing. The
main purpose of the meetings was for the Airport Authority, with
M its consultants, to show the EPD where in the EIA Report each M
comment was addressed. I and my colleagues, with our
consultants Mouchel and their sub-consultant, considered
N N
carefully all the comments raised, included Shui Wing’s concerns.
The EIA Report was considered to have covered all the
O comments.” (Mr W.O.W. Roberts, the Civil Engineering O
Manager for HKAA)
P P
“HS/APG have reviewed and commented on EAND response to
Q public comments including SW. There is now produced and Q
shown to me a copy of the comments marked exhibit ‘JW-2’.
I will now give further explanation of the important technical
R R
issues …” (Dr J. Wrigley)
S S
“During the public consultation period between 14 June 2002
and 14 July 2002, a total of 13 sets of comments were received
T T
by the EPD. The comments included comments from Shiu
U U
V V
由此
- 42 -
A A
Wing Steel Limited (‘SWS’) contained in a letter dated 13 July
B 2002… During this period, the public comments received were B
made available to the Secretary for the EIA Subcommittee
though there was no obligation on the part of EPD to do so. At
C C
the end of the consultation period, I conducted a preliminary
review of the comments and considered there were potentially
D major concerns expressed by the public. I therefore alerted all D
senior staff of the EPD including the Director, the Deputy
Director of Environmental Protection (‘Deputy Director’) and
E the Assistant Director of the concerns expressed, highlighting the E
major issues including those raised by SWS…
F F
After the public consultation period, staff of the EPD carried out
a thorough review of the issues raised by the public, collated
G them under different categories, discussed them with the HKAA G
and checked them against the EIA report. The staff of EPD
including myself were satisfied that the concerns appeared to
H H
have been fully addressed and, a set of detailed responses were
subsequently drafted …” (Mr Hui Yat Ming, a Principal
I Environmental Protection Officer) I
J J
(d) 25 April meeting
K K
96. This issue has been addressed earlier in this judgment. I do
L not consider there to be merit in the complaint that a decision was made L
behind closed doors and therefore to the disadvantages of the public. As
M M
already stated the EIA report is prepared in a “non public” period in the
N whole process. The basis of the risk assessment became public (namely N
the 10% loss of tank content scenario) and therefore open to scrutiny the
O O
moment the report was published. It is wrong to describe the Director as
P making a “belated admission” to this effect in August 2003. The P
consequence of the decision has been in the public domain since May 2002,
Q Q
and was affirmed to by Dr Wrigley in February 2003. Neither the TM
R nor the SB require disclosure of all the circumstances, considerations, R
deliberations and reasons which led up to any particular judgment or
S S
decision being made.
T T
U U
V V
由此
- 43 -
A A
97. In short it is suggested that because a decision concerning
B B
the content of the EIA report was made between the Director and the
C HKAA, (at the highest level and by acknowledged experts) at a time when C
there was no provision for public involvement, was Wednesbury
D D
unreasonable because it “surrendered the process to private agreement”.
E I consider this submission to be circular and illogical. E
F F
98. In any event, it is worthy to note that this complaint is not set
G out in SWS’s notice of application. The respondent and interested party G
have therefore not had an opportunity of filing evidence about it.
H H
I (e) Safeguards and conditions I
J 99. SWS’s complaint is that the Director has granted J
environmental approval and permission without ensuring that the full
K K
details of the project are fixed with certainty.
L L
100. Section 10(5) of the EIAO permits the granting of a permit
M M
with conditions. Section 9 makes the conditions enforceable and
N N
section 14 provides for the suspension of the project if the conditions are
O
not complied with. O
P P
101. SWS refers to an extract from Mr Hui Yat Ming’s affirmation
Q as the basis of the complaint : Q
“[w]here the particular [mitigation] measure is complex, difficult
R R
to express, or contain details not readily available during the EIA
stage, further submissions may be required to ensure that the
S project will be designed in line with the assumptions in the EIA S
while providing the necessary flexibility for minor project
changes.”
T T
U U
V V
由此
- 44 -
A A
102. It is argued that this amounts to an admission that the Director
B B
did not have sufficient information on which to base a decision that the
C qualitative assessment was sufficient and that the Director allowed HKAA C
to delay providing important technical information about the project.
D D
E 103. To interpret Mr Hui’s evidence in this way reads too much E
into it. No complaint can be made that the Director in acting in
F F
accordance with his powers acted unreasonably in the Wednesbury sense.
G That it could have been unlawful and outside his powers is unsustainable. G
H H
104. The role of conditions was considered and commented on in
I the “Long Valley” appeal : I
J “… Where a report is approved and permit granted, however, J
important steps in the process follow. These are:-
K K
a. The Director will often impose conditions on both the report
and the permit (see Schedule 4 of the Ordinance). These
L are to ensure (for example) that Habitat Creation and L
Maintenance Plans and Environmental Monitoring and Audit
Programmes outlined in the Report are later approved; that
M M
mitigation measures and the like are in place and satisfactory
before the project proceeds.
N N
b. The report will be placed in the register under section 8(5).
This is available for public inspection and if relevant may be
O relied upon for the granting of a permit for other projects O
without a further EIA study and report.
P P
c. The Director continues to monitor compliance before, during
and after construction and will if necessary use his
Q considerable powers under the enforcement provisions of the Q
Ordinance.
R There is a difference in emphasis between conditions to the R
approval of a report, which usually are to ensure that matters
dealt with in the report are completed. The Director’s approval
S S
of a Habitat Creation Plan for example. The conditions to a
permit are related to the construction work and are to ensure that
T the report is complied with before, during and after construction. T
U U
V V
由此
- 45 -
A A
For example a condition that a mitigation area is functioning
B before construction begins.” B
C Conditions enable matters of detail to be dealt with at a later stage. C
D D
105. Before I turn to the final section of this decision (namely the
E issue of discretion), I think it appropriate at this stage to deal briefly with E
an important point, hitherto unmentioned. The exhaustive EIA process,
F F
starting with the project profile, going through the SB, TM and report stage,
G on to the approval, permit and conditions stage is but one statutory control G
and safeguard in the construction of this important but sensitive installation.
H H
The Buildings Department, the Fire Services Department, the Marine
I Department and the Lands Department are others who exercise stringent I
statutory control over the project. The approval of the report and the
J J
granting of the permit under the EIAO is just one of a number of approvals
K K
to be sought. This court’s decision that the Director’s decision should not
L
be reviewed is one piece in a bigger picture. That is not to say that L
because there are other statutory schemes in place anything less than the
M M
highest standards of expertise and competence will do when the crucial
N decisions are made. It merely serves to show that these same tanks, bund N
wall, fuel properties and so on, will be scrutinized from a variety of
O O
different viewpoints.
P P
DISCRETION
Q Q
106. For the sake of completeness only, I make brief reference to
R R
the question of discretion. Remedies in judicial review are discretionary.
S In view of the decisions made I do not have to consider whether I should S
exercise a discretion not to grant any remedies even though a ground of
T T
judicial review has been made out.
U U
V V
由此
- 46 -
A A
107. However, had I found in favour of SWS on any one of the
B B
grounds of complaint, I address the issue of whether or not I would have
C exercised my discretion to decline to grant any relief. It would have been C
a difficult decision.
D D
E 108. At the end of the day I would have exercised the discretion in E
the Director’s favour. The outline reasons being :
F F
(a) that there was delay in commencing the proceedings. It is
G G
very arguable that the first decision which SWS submit was
H wrong was the section 6(3) decision. However no H
proceedings were commenced in relation to that decision
I I
although SWS’s original complaints plainly stem from the
content of the EIA report regardless of whether it was
J J
accepted or not. The section 6(3) decision was in June 2002,
K the section 8 and section 10 decisions were August. SWS’s K
letter of complaint had been in July but their original notice of
L L
application was not until 1 November 2002.
M (b) the crux of SWS’s case as presented at the hearing was largely M
technical in nature. It attacked the technical soundness of
N N
the EIA report based on expert opinion produced in the
O summer of 2003. Had the report been admitted and had the O
court decided a strict compliance with the letter of the TB and
P P
SB was required the outcome would have been that the
judicial review would have succeeded on the basis that it had
Q Q
been unlawful for the Director to carry a QRA on a scenario
R which was, based on the information available to the Director R
at the time, considered to be incredible.
S S
(c) In any event the case, as put in 2003, could have been made at
T the time of the public consultation but was not. T
U U
V V
由此
- 47 -
A A
(d) It is the court’s view that the sum of the evidence supports the
B B
submission that the same decision would be made now as was
C made in August 2002 notwithstanding the additional material C
which has been submitted.
D D
E 109. In short this court’s view would have been that the balancing E
exercise would have tilted in the respondent’s favour so that this particular
F F
major designated project would have been allowed to continue in the
G G
interest of the public at large and in the interest of good administration.
H H
110. All considerations concerning discretion are academic in view
I I
of the court’s primary conclusions.
J J
111. To conclude :
K K
(1) The Director’s decisions have been considered on the basis of
L the materials before him. L
M (2) SWS’s challenge that the decisions were unlawful based on M
the alleged failure to meet the requirements of the SB, the TM
N N
and the Ordinance have not been made out.
O (3) That challenge has been based, to a large extent, on the O
opinions in the HSL report which is inadmissible.
P P
(4) Were the post decision materials admissible they would have
Q resulted in a difference of expert opinion which itself would Q
not have altered the fact that the Director was acting within
R R
his power when he decided that the EIA report should be
approved as it complied with the SB and TM and that decision
S S
was not Wednesbury unreasonable.
T T
U U
V V
由此
- 48 -
A A
The answers to the five questions posed on pages 14 and 15 of this
B B
judgment are :
C C
(1) No.
D (2) Yes. D
E (3) Yes. E
(4) Not addressed as a separate issue.
F F
(5) Had the answers to (2) or (3) been different the discretion to,
G nonetheless, grant no relief would have been exercised. G
H H
112. This application is dismissed. The respondent’s and
I I
interested party’s costs are to be paid by the applicant.
J J
K K
L L
( M.P. Burrell )
M Judge of the Court of First Instance, M
High Court
N N
O O
Mr Charles Haddon-Cave, QC, Mr Nigel Pleming, QC and
Mr Anthony Chan, SC, instructed by Messrs Simmons & Simmons,
P P
for the Applicant
Q Mr Benjamin Yu, SC and Mr Anthony Ismail, instructed by Q
the Department of Justice, for the Respondent
R R
Ms Gladys Li, SC, instructed by Messrs Lovells, for the Interested Party
S S
T T
U U
V V