LDCS7000/2022 WINLAND PROPERTY HOLDING LTD AND OTHERS v. CHANG SAI HO formerly known as LAW WAI KUN AND OTHERS - LawHero
LDCS7000/2022
Lands TribunalMaster D To24/7/2025
LDCS7000/2022
A A
LDCS 7000/2022
B
[2025] HKLdT 41 B
C IN THE LANDS TRIBUNAL OF THE C
HONG KONG SPECIAL ADMINISTRATIVE REGION
D D
LAND COMPULSORY SALE MAIN APPLICATION NO 7000 OF 2022
E _________________ E
F F
BETWEEN
G WINLAND PROPERTY HOLDING 1st Applicant G
LIMITED
H H
(永倫興業有限公司)
I WINDLAND CENTRE LIMITED 2nd Applicant I
(永倫中心有限公司)
J J
rd
WINLAND CULTURE LIMITED 3 Applicant
K (永倫文化有限公司) K
and
L L
CHANG SAI HO (蔣世浩) formerly st
1 Respondent
M known as LAW WAI KUN (羅維根) M
VOLANT RICH LIMITED 2nd Respondent
N N
KANCO DEVELOPMENT LIMITED 3rd Respondent
O (奇高發展有限公司) O
____________________
P P
Before: Master D To in Chambers
Q Q
Date of Taxation Hearing: 18 June 2025
R Date of Handing Down Reasons for Decision on Preliminary Issue of R
Undue Delay: 25 July 2025
S S
T T
U U
V V
- 2 -
A A
REASONS FOR DECISION
B B
(Preliminary Issue of Undue Delay)
C C
D
Introduction D
1. Under paragraph 7 of the Judgment of the Lands Tribunal
E E
dated 28 March 2024 (“the Judgment”), the Applicants are ordered to pay
F F
the Respondents the costs of the proceedings (“the Costs Order”).
G G
2. On 5 November 2024, more than 7 months after the Costs
H Order, the 1st Respondent (“the Receiving Party”) commenced taxation H
proceedings by filing the Notice of Commencement of Taxation and the
I I
Bill of Costs (“the Bill of Costs”).
J J
3. On 6 January 2025, the 1st to 3rd Applicants (“the Paying
K K
Party”) filed their List of Objections to the Bill of Costs. They raised
L therein a preliminary issue of undue delay, asking the Court to disallow L
interest or part of the taxed costs in accordance with Order 62 rule 22(5) of
M M
Rules of the High Court (“RHC”).
N N
4. Pursuant to Order 62 rule 22(1) RHC, if within 3 months after
O O
the completion date, the Receiving Party has not agreed the amount of costs
P with the Paying Party, he shall commence taxation proceedings pursuant to P
Order 62 rule 21 RHC.
Q Q
R 5. Order 62 rule 22(5) RHC provides that R
S S
“….. the taxing master, if he is satisfied that there has been undue
delay in commencing taxation proceedings or in proceeding with
T the taxation – (a) may make such order as he thinks fir as to the T
costs of any application or as to the costs of the taxation; (b) may
U U
V V
- 3 -
A A
disallow any part of the costs to be taxed pursuant to the costs
B order; and (c) may, in relation to the taxed costs or any part of B
those costs, disallow interest or reduce the period for which
interest is payable or the rate at which interest is payable.”
C C
6. The Paying Party’s complaint was that the Receiving party
D D
should have commenced taxation proceedings on or before 27 June 2024,
E i.e. within 3 months of 28 March 2024 when the Costs Order was made. E
There was undue delay of more than 4 months from 28 June 2024 to
F F
4 November 2024, so the Receiving Party should be deprived of interest
G on the taxed costs for such period. G
H H
7. First of all, taking 28 March 2024 as the completion date is
I not correct. Since the Costs Order was an order nisi, according to Order I
62 rule 22(9)(a)(ii) RHC, the completion date should be the date on which
J J
the Costs Order is made absolute, i.e. 11 April 2024. Therefore, the delay
K in commencing taxation proceedings is less than 4 months from 11 July K
2024 to 4 November 2024.
L L
M 8. At the taxation hearing on 18 June 2025, the Bill of Costs was M
taxed. There is no application within the prescribed time limit under
N N
Order 62 rule 33 RHC to review my determination in respect of the taxed
O costs. Regarding the preliminary issue of undue delay, I ruled in favor of O
the Receiving Party that there was no undue delay to attract sanction under
P P
Order 62 rule 22(5) RHC, with reasons I now give.
Q Q
Duty on Both Parties
R R
S 9. In most if not all cases when the paying party raises the issue S
of undue delay, the receiving party will seek to rely on the case of
T T
Commissioner of Inland Revenue v Li & Fung (Trading) Ltd [2014] 4 HKC
U U
V V
- 4 -
A A
61 as a shield. In it, Master Levy ruled that while the receiving party bore
B B
the ultimate responsibility of commencing taxation without delay, the
C paying party is also required to further the underlying objectives of Order C
1A rule 3 RHC and to resort to the protection accorded under Order 62 rule
D D
22(3) RHC i.e. to compel a receiving party to commence taxation. If the
E paying party does not, and chose to take a passive approach, he cannot later E
take advantage of the receiving party’s delay.
F F
G 10. The Receiving Party in addition to his primary argument that G
the delay is not undue, also advanced the above argument that the complete
H H
inaction on the part of the Paying Party disentitled them of the relief under
I Order 62 rule 22(5) RHC. I
J J
11. I am of the view that the Paying Party’s inaction alone cannot
K be the Receiving Party’s shield to escape sanction for undue delay if any. K
While the duty is on both parties, if the Paying Party under inaction cannot
L L
reap the benefit of delay, neither can the Receiving Party take advantage of
M the Paying Party’s inaction. M
N N
12. In order to reflect the respective accountability for undue
O
delay and inaction, the practice of some taxing masters is to apportion the O
blame and disallow half of the interest of the taxed costs for the relevant
P P
period. How discretion is to be exercised will depend on the facts of each
Q case. Q
R R
Relevant Events in Chronological Order
S S
13. The delay for the period from 11 July 2024 to 4 November
T 2024 will be considered against the following events in chronological order. T
U U
V V
- 5 -
A A
11 April 2024 Completion date
B B
C 10 July 2024 the 3-month period under Order 62 rule 22(1) C
expired
D D
E
16 July 2024 Receiving Party initiated settlement negotiation E
by providing Paying Party with an estimate of
F F
costs. There was no response from Paying
G Party G
H H
August 2024 Receiving Party instructed Law Costs Draftsman
I
(“LCD”) to prepare bill of costs I
J 17 October 2024 Receiving Party provided Paying Party with J
copy draft bill of costs with a view to negotiate
K K
for settlement. There was no response from
L Paying Party L
M M
5 November 2024 commencement of taxation proceedings
N N
14. The Receiving Party has neither negotiated costs nor
O O
commenced taxation within the required period of 3 months under Order
P 62 rule 22(1) RHC. P
Q Q
The 3-month Requirement
R R
15. The 3-month period after the completion date was to enable
S S
parties to have time to actively negotiate for settlement, and when there
T T
U U
V V
- 6 -
A A
was no prospect of agreement, to start preparing the bill of costs timely
B B
such that it would be ready for filing before the 3-month period expires.
C C
16. Noticeably, practitioners taking the 3-month requirement
D D
light-heartedly has somehow become the norm in conducting taxation
E proceedings. Many solicitors for the receiving party are slack and loose E
during the 3-month period without taking active steps. Some even think
F F
that there is a 2-year period to commence taxation proceedings; this is of
G course misconceived. The 2-year limitation under Order 62 rule 22(7) G
RHC is a time bar provision; it operates differently from the 3-month
H H
requirement.
I I
17. In order to strictly comply with the 3-month requirement,
J J
solicitors for the receiving party should discipline themselves by devising
K and following a timetable, ensuring that all necessary tasks are addressed K
at appropriate times. What should the timetable be like?
L L
M
18. I am of the view that the following timetable (subject to M
necessary modifications and adjustments) is definitely achievable within
N N
the 3-month period, as long as solicitors for the receiving party act in all
O
diligence and with utmost sincerity to observe the rules. O
P P
(a) Within 7 days of the completion date, provide the paying party
Q with an estimate of costs to initiate negotiation; Q
(b) There being no response or no settlement reached within 14
R R
days thereafter, immediately proceed to instruct Law Costs
S
Draftsman to prepare the bill of costs, to be ready within 28 S
days;
T T
U U
V V
- 7 -
A A
(c) Within 7 days thereafter, the draft bill of costs be approved by
B B
instructing solicitors and copy of the same be provided to the
C paying party; C
(d) There being no response or no settlement reached within 21
D D
days thereafter, proceed immediately to prepare the Notice of
E Commencement of Taxation and finalize the draft bill of costs E
in order that taxation proceedings is commenced under Order
F F
62 rule 21 RHC within the next 7 days.
G G
19. Two points have to be emphasized. First, the need to
H accommodate LCD’s workload or personal engagement does not justify H
delay in commencing taxation proceedings. I note that it is not
I I
uncommon LCDs take months to prepare the bill of costs; probably
J because they have an over-whelming amount of tasks at one time, hence J
sitting on the papers causing the delay. If this is permitted to continue,
K K
the purpose of the 3-month requirement can hardly be achieved. To
L regulate the existing practice, if the intended LCD upon instructions is L
unable to commit himself/herself to finish preparing the bill of costs within
M M
28 days, another available LCD ought to be instructed.
N N
20. I regard 28 days reasonable and more than sufficient for LCD
O O
to prepare the bill of costs.
P P
(a) Firstly, before the CJR the time previously allowed for
Q Q
commencing taxation was only one month from the
R completion date. The change to three months was to enable R
parties to have time to actively negotiate for settlement; it was
S never meant for giving LCDs more time to prepare the bill of S
costs.
T T
U U
V V
- 8 -
A A
(b) Further, as evident from the usual claim for LCD’s costs in
B B
preparing a bill of costs, even for a bill that is considerably
C complicated, it rarely requires more than 80 hours of work. C
D 21. Second, on-going settlement negotiation does not ipso facto D
justify delay of commencement of taxation proceedings although one of
E E
the underlying objectives under Order 1A rule 1(e) RHC is to facilitate the
F settlement of disputes. F
G G
22. If there is genuine intention to settle, the commencement of
H taxation proceedings would not affect parties’ attempt to further their H
negotiation thereafter. In case parties are very close to reaching a
I I
settlement when the 3-month period is about to expire, for the purpose of
J saving costs, it is practical that a joint application be made to the court for J
extension of time to commence taxation.
K K
L 23. As discussed above, it is high time we straightened and L
regulated the pervading bad habit of delay in the conduct of taxation
M M
proceedings.
N N
The Alleged Undue Delay
O O
P 24. To attract sanction of Order 62 rule 22(5) RHC, there has to P
be undue delay, a delay which is unwarranted, inordinate and unjustifiable.
Q Q
Whether a delay can be reasonably explained will depend on the
R circumstances of each case. R
S S
25. In the present case, the Receiving Party failed to initiate
T
settlement negotiations nor prepare the bill of costs before 11 July 2024. T
Explanation is as follows. By the Judgment, the Lands Tribunal adjudged
U U
V V
- 9 -
A A
inter alia that the subject Lot be sold by way of public auction for the
B B
purposes of redevelopment of the Lot, on the particulars and conditions of
C sale “substantially the same as those in the draft Particulars and Conditions C
of Sale” initialed and approved by the Tribunal. Therefore, there was the
D D
paragraph 6 in the Judgment expressly giving parties liberty to apply to the
E Tribunal for further directions. E
F F
26. The Receiving Party submitted that the public auction was
G scheduled to take place on 14 May 2024, after the Judgment parties were G
actively engaged in discussion concerning the draft Particulars and
H H
Conditions of Sale. Matters transpired that they had to seek further
I directions from the Lands Tribunal concerning the conditions of sale. It I
is submitted that it is justifiable the Receiving Party withheld
J J
commencement of taxation proceedings because the seeking of further
K directions from the Lands Tribunal may impact on the ultimate scope of K
the Costs Order.
L L
M 27. The Paying Party submitted that notwithstanding parties had M
to seek further directions from the Lands Tribunal, the Receiving Party
N N
should have commenced taxation proceedings without delay. The Paying
O Party argued that seeking further directions from the Lands Tribunal would O
not have any bearing on setting off parties’ liability for costs; but it does
P P
not dispute that there is possible impact on the ultimate scope of the Costs
Q Order. Q
R R
28. Having considered parties’ argument in light of the relevant
S background, I am persuaded that the Receiving Party did not lie idly. S
When the public auction was pressing, there was an imminent need to
T T
finalize the particulars and conditions of sale. I accept that it is excusable
U U
V V
- 10 -
A A
to focus the effort thereon and withhold commencement of taxation
B B
proceedings for the time being. Further, it is practical to wait until further
C directions of the court were sought, because it may impact on the ultimate C
scope of the Costs Order.
D D
E 29. Notwithstanding that inaction during the 3-month period is E
reasonably explained as above, justification is still required as to why
F F
taxation proceedings were only commenced on 5 November 2024 and not
G earlier. G
H H
30. LCD was instructed in August 2024. There is no
I explanation why it was not until 17 October 2024 the Paying Party was I
provided with a copy draft bill of costs. Although it is unclear to me
J J
whether there was delay on the part of the LCD, it is clear that the draft bill
K of costs could and should have been made available for the Paying Party K
much earlier, noting that the claim for LCD’s costs in preparing the bill is
L L
35 hours.
M M
31. The Receiving Party submitted that the Paying Party was the
N N
one who caused or contributed to the delay. Much time was spent in
O
waiting for the Paying Party’s response to the estimate of costs provided O
on 16 July 2024 and the draft bill of costs provided on 17 October 2024.
P P
However, there was no response at all.
Q Q
32. Worse still, there was no explanation of the neglect or refusal
R R
to respond. This attitude of the solicitors of the Paying Party is wholly
S
unacceptable, instead they pointed fingers and placed blame on the S
Receiving Party.
T T
U U
V V
- 11 -
A A
33. Having considered matters in the round, I do not think the
B B
Receiving Party’s delay is inordinate or inexcusable, although the progress
C between August and October 2024 could have been expedited. I find that C
there was no undue delay to attract sanction under Order 62 rule 22(5) RHC.
D D
E E
(D To)
F F
Master of the High Court
G G
H H
I I
J J
K K
L L
M M
N N
O O
P Mr Barry Leung, Law Costs Draftsman, instructed by Messrs So, Lung & P
Associates, solicitors for the 1st Respondent/Receiving Party
Q Q
Mr Jimmy Tzu, Law Costs Draftsman, instructed by Messrs Lo & Lo,
R solicitors for the 1st to 3rd Applicants/Paying Party R
S S
T T
U U
V V
WINLAND PROPERTY HOLDING LTD AND OTHERS v. CHANG SAI HO formerly known as LAW WAI KUN AND OTHERS
案件基本資料
案件名稱:Winland Property Holding Limited & others v Chang Sai Ho & others
法院:土地審裁處 (Lands Tribunal)
法官:Master D To
判決日期:2025年7月25日
案情摘要
本案涉及土地強制出售申請。法院於2024年3月28日發出 Costs Order 要求申請人支付答辯人的訟費。第一答辯人(Receiving Party)於2024年11月5日啟動 taxation proceedings。申請人(Paying Party)質疑該程序啟動過遲,違反了 RHC Order 62 rule 22(1) 規定的3個月期限,要求根據 Order 62 rule 22(5) 扣除利息或部分訟費。
核心法律爭議
核心 legal issue 係 Receiving Party 啟動 taxation proceedings 的延遲是否構成 "undue delay",足以觸發 Order 62 rule 22(5) 的制裁。Paying Party 主張延遲超過4個月,應被剝奪利息;Receiving Party 則辯稱延遲有合理理由,且 Paying Party 採取被動態度未採取行動促使 taxation 啟動。
判決理由
法官認為 "undue delay" 必須是 unwarranted, inordinate 及 unjustifiable。雖然 Receiving Party 未在3個月內啟動程序,但當時正處理拍賣條件及尋求法院指示,可能影響 Costs Order 範圍,屬合理延遲。此外,法官指出 Paying Party 對成本估算及草擬單據完全不回應,其被動態度亦不應成為其要求制裁的理由。法官同時強調,LCD 準備單據的時間不應成為延遲的藉口,並建議律師應制定嚴格的時間表以遵守 3-month requirement。
引用案例與條文
引用 Commissioner of Inland Revenue v Li & Fung (Trading) Ltd [2014] 4 HKC 61,探討 Receiving Party 與 Paying Party 對啟動 taxation 的共同責任,但法官認為 Paying Party 的不作為不能成為 Receiving Party 逃避制裁的絕對 shield。
裁決與命令
法官裁定 Receiving Party 並無 undue delay,因此不適用 Order 62 rule 22(5) RHC 的制裁,Ruling 判定 Receiving Party 勝訴。
### 案件基本資料
- 案件名稱:Winland Property Holding Limited & others v Chang Sai Ho & others
- 法院:土地審裁處 (Lands Tribunal)
- 法官:Master D To
- 判決日期:2025年7月25日
### 案情摘要
本案涉及土地強制出售申請。法院於2024年3月28日發出 Costs Order 要求申請人支付答辯人的訟費。第一答辯人(Receiving Party)於2024年11月5日啟動 taxation proceedings。申請人(Paying Party)質疑該程序啟動過遲,違反了 RHC Order 62 rule 22(1) 規定的3個月期限,要求根據 Order 62 rule 22(5) 扣除利息或部分訟費。
### 核心法律爭議
核心 legal issue 係 Receiving Party 啟動 taxation proceedings 的延遲是否構成 "undue delay",足以觸發 Order 62 rule 22(5) 的制裁。Paying Party 主張延遲超過4個月,應被剝奪利息;Receiving Party 則辯稱延遲有合理理由,且 Paying Party 採取被動態度未採取行動促使 taxation 啟動。
### 判決理由
法官認為 "undue delay" 必須是 unwarranted, inordinate 及 unjustifiable。雖然 Receiving Party 未在3個月內啟動程序,但當時正處理拍賣條件及尋求法院指示,可能影響 Costs Order 範圍,屬合理延遲。此外,法官指出 Paying Party 對成本估算及草擬單據完全不回應,其被動態度亦不應成為其要求制裁的理由。法官同時強調,LCD 準備單據的時間不應成為延遲的藉口,並建議律師應制定嚴格的時間表以遵守 3-month requirement。
### 引用案例與條文
引用 Commissioner of Inland Revenue v Li & Fung (Trading) Ltd [2014] 4 HKC 61,探討 Receiving Party 與 Paying Party 對啟動 taxation 的共同責任,但法官認為 Paying Party 的不作為不能成為 Receiving Party 逃避制裁的絕對 shield。
### 裁決與命令
法官裁定 Receiving Party 並無 undue delay,因此不適用 Order 62 rule 22(5) RHC 的制裁,Ruling 判定 Receiving Party 勝訴。
### 判決啟示
法官對目前法律實務中輕視 3-month requirement 的現象表示不滿,並在判決書中詳細列出一個建議的 taxation 準備時間表(例如:7天內提供估算、28天內由 LCD 完成單據),旨在規範律師及 LCD 的工作習慣,防止不合理的延遲。
---
### 免責聲明
本摘要由人工智能自動生成,內容可能存在錯誤或遺漏,僅供參考,不構成法律意見。如需法律建議,請諮詢合資格律師。### Case Details
- Case Name: Winland Property Holding Limited & others v Chang Sai Ho & others
- Court: Lands Tribunal
- Judge: Master D To
- Date of Judgment: 25 July 2025
### Factual Background
Following a Costs Order dated 28 March 2024 in a land compulsory sale application, the 1st Respondent (Receiving Party) commenced taxation proceedings on 5 November 2024. The Applicants (Paying Party) raised a preliminary issue of undue delay, arguing that the proceedings were started beyond the 3-month window prescribed by Order 62 rule 22(1) RHC, and sought sanctions under Order 62 rule 22(5) RHC.
### Key Legal Issues
The core legal issue was whether the delay in commencing taxation proceedings constituted "undue delay" (unwarranted, inordinate, and unjustifiable) sufficient to trigger sanctions, such as the disallowance of interest or part of the costs. The Paying Party argued the delay was excessive, while the Receiving Party contended it was justified by ongoing court directions and the Paying Party's own inaction.
### Ratio Decidendi
The judge found no undue delay. The delay was reasonably explained by the need to finalize auction conditions and seek further directions from the Tribunal, which could have impacted the scope of the Costs Order. Furthermore, the Paying Party's total failure to respond to cost estimates and draft bills was deemed unacceptable. The judge emphasized that the 3-month requirement is intended for settlement negotiations, not to provide Law Costs Draftsmen (LCDs) extra time to prepare bills.
### Key Precedents & Statutes
Commissioner of Inland Revenue v Li & Fung (Trading) Ltd [2014] 4 HKC 61 was cited regarding the mutual duty of both parties to further taxation proceedings, although the judge noted that a Paying Party's inaction cannot be used as a total shield by the Receiving Party.
### Decision & Orders
The judge ruled in favor of the Receiving Party, finding that there was no undue delay to attract sanctions under Order 62 rule 22(5) RHC.
### Key Takeaways
The judgment criticizes the professional habit of treating the 3-month requirement lightly. Notably, the judge provided a detailed recommended timetable for solicitors and LCDs to ensure strict compliance with taxation rules, signaling a move toward stricter regulation of taxation conduct.
---
### Disclaimer
This summary is AI-generated and may contain errors or omissions. It is for reference only and does not constitute legal advice. Please consult a qualified lawyer for professional legal advice.
A A
LDCS 7000/2022
B
[2025] HKLdT 41 B
C IN THE LANDS TRIBUNAL OF THE C
HONG KONG SPECIAL ADMINISTRATIVE REGION
D D
LAND COMPULSORY SALE MAIN APPLICATION NO 7000 OF 2022
E _________________ E
F F
BETWEEN
G WINLAND PROPERTY HOLDING 1st Applicant G
LIMITED
H H
(永倫興業有限公司)
I WINDLAND CENTRE LIMITED 2nd Applicant I
(永倫中心有限公司)
J J
rd
WINLAND CULTURE LIMITED 3 Applicant
K (永倫文化有限公司) K
and
L L
CHANG SAI HO (蔣世浩) formerly st
1 Respondent
M known as LAW WAI KUN (羅維根) M
VOLANT RICH LIMITED 2nd Respondent
N N
KANCO DEVELOPMENT LIMITED 3rd Respondent
O (奇高發展有限公司) O
____________________
P P
Before: Master D To in Chambers
Q Q
Date of Taxation Hearing: 18 June 2025
R Date of Handing Down Reasons for Decision on Preliminary Issue of R
Undue Delay: 25 July 2025
S S
T T
U U
V V
- 2 -
A A
REASONS FOR DECISION
B B
(Preliminary Issue of Undue Delay)
C C
D
Introduction D
1. Under paragraph 7 of the Judgment of the Lands Tribunal
E E
dated 28 March 2024 (“the Judgment”), the Applicants are ordered to pay
F F
the Respondents the costs of the proceedings (“the Costs Order”).
G G
2. On 5 November 2024, more than 7 months after the Costs
H Order, the 1st Respondent (“the Receiving Party”) commenced taxation H
proceedings by filing the Notice of Commencement of Taxation and the
I I
Bill of Costs (“the Bill of Costs”).
J J
3. On 6 January 2025, the 1st to 3rd Applicants (“the Paying
K K
Party”) filed their List of Objections to the Bill of Costs. They raised
L therein a preliminary issue of undue delay, asking the Court to disallow L
interest or part of the taxed costs in accordance with Order 62 rule 22(5) of
M M
Rules of the High Court (“RHC”).
N N
4. Pursuant to Order 62 rule 22(1) RHC, if within 3 months after
O O
the completion date, the Receiving Party has not agreed the amount of costs
P with the Paying Party, he shall commence taxation proceedings pursuant to P
Order 62 rule 21 RHC.
Q Q
R 5. Order 62 rule 22(5) RHC provides that R
S S
“….. the taxing master, if he is satisfied that there has been undue
delay in commencing taxation proceedings or in proceeding with
T the taxation – (a) may make such order as he thinks fir as to the T
costs of any application or as to the costs of the taxation; (b) may
U U
V V
- 3 -
A A
disallow any part of the costs to be taxed pursuant to the costs
B order; and (c) may, in relation to the taxed costs or any part of B
those costs, disallow interest or reduce the period for which
interest is payable or the rate at which interest is payable.”
C C
6. The Paying Party’s complaint was that the Receiving party
D D
should have commenced taxation proceedings on or before 27 June 2024,
E i.e. within 3 months of 28 March 2024 when the Costs Order was made. E
There was undue delay of more than 4 months from 28 June 2024 to
F F
4 November 2024, so the Receiving Party should be deprived of interest
G on the taxed costs for such period. G
H H
7. First of all, taking 28 March 2024 as the completion date is
I not correct. Since the Costs Order was an order nisi, according to Order I
62 rule 22(9)(a)(ii) RHC, the completion date should be the date on which
J J
the Costs Order is made absolute, i.e. 11 April 2024. Therefore, the delay
K in commencing taxation proceedings is less than 4 months from 11 July K
2024 to 4 November 2024.
L L
M 8. At the taxation hearing on 18 June 2025, the Bill of Costs was M
taxed. There is no application within the prescribed time limit under
N N
Order 62 rule 33 RHC to review my determination in respect of the taxed
O costs. Regarding the preliminary issue of undue delay, I ruled in favor of O
the Receiving Party that there was no undue delay to attract sanction under
P P
Order 62 rule 22(5) RHC, with reasons I now give.
Q Q
Duty on Both Parties
R R
S 9. In most if not all cases when the paying party raises the issue S
of undue delay, the receiving party will seek to rely on the case of
T T
Commissioner of Inland Revenue v Li & Fung (Trading) Ltd [2014] 4 HKC
U U
V V
- 4 -
A A
61 as a shield. In it, Master Levy ruled that while the receiving party bore
B B
the ultimate responsibility of commencing taxation without delay, the
C paying party is also required to further the underlying objectives of Order C
1A rule 3 RHC and to resort to the protection accorded under Order 62 rule
D D
22(3) RHC i.e. to compel a receiving party to commence taxation. If the
E paying party does not, and chose to take a passive approach, he cannot later E
take advantage of the receiving party’s delay.
F F
G 10. The Receiving Party in addition to his primary argument that G
the delay is not undue, also advanced the above argument that the complete
H H
inaction on the part of the Paying Party disentitled them of the relief under
I Order 62 rule 22(5) RHC. I
J J
11. I am of the view that the Paying Party’s inaction alone cannot
K be the Receiving Party’s shield to escape sanction for undue delay if any. K
While the duty is on both parties, if the Paying Party under inaction cannot
L L
reap the benefit of delay, neither can the Receiving Party take advantage of
M the Paying Party’s inaction. M
N N
12. In order to reflect the respective accountability for undue
O
delay and inaction, the practice of some taxing masters is to apportion the O
blame and disallow half of the interest of the taxed costs for the relevant
P P
period. How discretion is to be exercised will depend on the facts of each
Q case. Q
R R
Relevant Events in Chronological Order
S S
13. The delay for the period from 11 July 2024 to 4 November
T 2024 will be considered against the following events in chronological order. T
U U
V V
- 5 -
A A
11 April 2024 Completion date
B B
C 10 July 2024 the 3-month period under Order 62 rule 22(1) C
expired
D D
E
16 July 2024 Receiving Party initiated settlement negotiation E
by providing Paying Party with an estimate of
F F
costs. There was no response from Paying
G Party G
H H
August 2024 Receiving Party instructed Law Costs Draftsman
I
(“LCD”) to prepare bill of costs I
J 17 October 2024 Receiving Party provided Paying Party with J
copy draft bill of costs with a view to negotiate
K K
for settlement. There was no response from
L Paying Party L
M M
5 November 2024 commencement of taxation proceedings
N N
14. The Receiving Party has neither negotiated costs nor
O O
commenced taxation within the required period of 3 months under Order
P 62 rule 22(1) RHC. P
Q Q
The 3-month Requirement
R R
15. The 3-month period after the completion date was to enable
S S
parties to have time to actively negotiate for settlement, and when there
T T
U U
V V
- 6 -
A A
was no prospect of agreement, to start preparing the bill of costs timely
B B
such that it would be ready for filing before the 3-month period expires.
C C
16. Noticeably, practitioners taking the 3-month requirement
D D
light-heartedly has somehow become the norm in conducting taxation
E proceedings. Many solicitors for the receiving party are slack and loose E
during the 3-month period without taking active steps. Some even think
F F
that there is a 2-year period to commence taxation proceedings; this is of
G course misconceived. The 2-year limitation under Order 62 rule 22(7) G
RHC is a time bar provision; it operates differently from the 3-month
H H
requirement.
I I
17. In order to strictly comply with the 3-month requirement,
J J
solicitors for the receiving party should discipline themselves by devising
K and following a timetable, ensuring that all necessary tasks are addressed K
at appropriate times. What should the timetable be like?
L L
M
18. I am of the view that the following timetable (subject to M
necessary modifications and adjustments) is definitely achievable within
N N
the 3-month period, as long as solicitors for the receiving party act in all
O
diligence and with utmost sincerity to observe the rules. O
P P
(a) Within 7 days of the completion date, provide the paying party
Q with an estimate of costs to initiate negotiation; Q
(b) There being no response or no settlement reached within 14
R R
days thereafter, immediately proceed to instruct Law Costs
S
Draftsman to prepare the bill of costs, to be ready within 28 S
days;
T T
U U
V V
- 7 -
A A
(c) Within 7 days thereafter, the draft bill of costs be approved by
B B
instructing solicitors and copy of the same be provided to the
C paying party; C
(d) There being no response or no settlement reached within 21
D D
days thereafter, proceed immediately to prepare the Notice of
E Commencement of Taxation and finalize the draft bill of costs E
in order that taxation proceedings is commenced under Order
F F
62 rule 21 RHC within the next 7 days.
G G
19. Two points have to be emphasized. First, the need to
H accommodate LCD’s workload or personal engagement does not justify H
delay in commencing taxation proceedings. I note that it is not
I I
uncommon LCDs take months to prepare the bill of costs; probably
J because they have an over-whelming amount of tasks at one time, hence J
sitting on the papers causing the delay. If this is permitted to continue,
K K
the purpose of the 3-month requirement can hardly be achieved. To
L regulate the existing practice, if the intended LCD upon instructions is L
unable to commit himself/herself to finish preparing the bill of costs within
M M
28 days, another available LCD ought to be instructed.
N N
20. I regard 28 days reasonable and more than sufficient for LCD
O O
to prepare the bill of costs.
P P
(a) Firstly, before the CJR the time previously allowed for
Q Q
commencing taxation was only one month from the
R completion date. The change to three months was to enable R
parties to have time to actively negotiate for settlement; it was
S never meant for giving LCDs more time to prepare the bill of S
costs.
T T
U U
V V
- 8 -
A A
(b) Further, as evident from the usual claim for LCD’s costs in
B B
preparing a bill of costs, even for a bill that is considerably
C complicated, it rarely requires more than 80 hours of work. C
D 21. Second, on-going settlement negotiation does not ipso facto D
justify delay of commencement of taxation proceedings although one of
E E
the underlying objectives under Order 1A rule 1(e) RHC is to facilitate the
F settlement of disputes. F
G G
22. If there is genuine intention to settle, the commencement of
H taxation proceedings would not affect parties’ attempt to further their H
negotiation thereafter. In case parties are very close to reaching a
I I
settlement when the 3-month period is about to expire, for the purpose of
J saving costs, it is practical that a joint application be made to the court for J
extension of time to commence taxation.
K K
L 23. As discussed above, it is high time we straightened and L
regulated the pervading bad habit of delay in the conduct of taxation
M M
proceedings.
N N
The Alleged Undue Delay
O O
P 24. To attract sanction of Order 62 rule 22(5) RHC, there has to P
be undue delay, a delay which is unwarranted, inordinate and unjustifiable.
Q Q
Whether a delay can be reasonably explained will depend on the
R circumstances of each case. R
S S
25. In the present case, the Receiving Party failed to initiate
T
settlement negotiations nor prepare the bill of costs before 11 July 2024. T
Explanation is as follows. By the Judgment, the Lands Tribunal adjudged
U U
V V
- 9 -
A A
inter alia that the subject Lot be sold by way of public auction for the
B B
purposes of redevelopment of the Lot, on the particulars and conditions of
C sale “substantially the same as those in the draft Particulars and Conditions C
of Sale” initialed and approved by the Tribunal. Therefore, there was the
D D
paragraph 6 in the Judgment expressly giving parties liberty to apply to the
E Tribunal for further directions. E
F F
26. The Receiving Party submitted that the public auction was
G scheduled to take place on 14 May 2024, after the Judgment parties were G
actively engaged in discussion concerning the draft Particulars and
H H
Conditions of Sale. Matters transpired that they had to seek further
I directions from the Lands Tribunal concerning the conditions of sale. It I
is submitted that it is justifiable the Receiving Party withheld
J J
commencement of taxation proceedings because the seeking of further
K directions from the Lands Tribunal may impact on the ultimate scope of K
the Costs Order.
L L
M 27. The Paying Party submitted that notwithstanding parties had M
to seek further directions from the Lands Tribunal, the Receiving Party
N N
should have commenced taxation proceedings without delay. The Paying
O Party argued that seeking further directions from the Lands Tribunal would O
not have any bearing on setting off parties’ liability for costs; but it does
P P
not dispute that there is possible impact on the ultimate scope of the Costs
Q Order. Q
R R
28. Having considered parties’ argument in light of the relevant
S background, I am persuaded that the Receiving Party did not lie idly. S
When the public auction was pressing, there was an imminent need to
T T
finalize the particulars and conditions of sale. I accept that it is excusable
U U
V V
- 10 -
A A
to focus the effort thereon and withhold commencement of taxation
B B
proceedings for the time being. Further, it is practical to wait until further
C directions of the court were sought, because it may impact on the ultimate C
scope of the Costs Order.
D D
E 29. Notwithstanding that inaction during the 3-month period is E
reasonably explained as above, justification is still required as to why
F F
taxation proceedings were only commenced on 5 November 2024 and not
G earlier. G
H H
30. LCD was instructed in August 2024. There is no
I explanation why it was not until 17 October 2024 the Paying Party was I
provided with a copy draft bill of costs. Although it is unclear to me
J J
whether there was delay on the part of the LCD, it is clear that the draft bill
K of costs could and should have been made available for the Paying Party K
much earlier, noting that the claim for LCD’s costs in preparing the bill is
L L
35 hours.
M M
31. The Receiving Party submitted that the Paying Party was the
N N
one who caused or contributed to the delay. Much time was spent in
O
waiting for the Paying Party’s response to the estimate of costs provided O
on 16 July 2024 and the draft bill of costs provided on 17 October 2024.
P P
However, there was no response at all.
Q Q
32. Worse still, there was no explanation of the neglect or refusal
R R
to respond. This attitude of the solicitors of the Paying Party is wholly
S
unacceptable, instead they pointed fingers and placed blame on the S
Receiving Party.
T T
U U
V V
- 11 -
A A
33. Having considered matters in the round, I do not think the
B B
Receiving Party’s delay is inordinate or inexcusable, although the progress
C between August and October 2024 could have been expedited. I find that C
there was no undue delay to attract sanction under Order 62 rule 22(5) RHC.
D D
E E
(D To)
F F
Master of the High Court
G G
H H
I I
J J
K K
L L
M M
N N
O O
P Mr Barry Leung, Law Costs Draftsman, instructed by Messrs So, Lung & P
Associates, solicitors for the 1st Respondent/Receiving Party
Q Q
Mr Jimmy Tzu, Law Costs Draftsman, instructed by Messrs Lo & Lo,
R solicitors for the 1st to 3rd Applicants/Paying Party R
S S
T T
U U
V V